31/07/2026

🚧 Scarr Street Works Update 🚧

Works are progressing well through Stage 3 (north-east section), with stormwater, water main and irrigation works now over 70% complete. Businesses remain open and operating as normal.

Our next phase includes the installation of electrical conduits, with preparations underway for Stage 4, the busiest section of Scarr Street, following the reopening of the King Street intersection.

As concrete works commence, sections of temporary
fencing will be removed and updated traffic management arrangements will be implemented to maintain safe pedestrian and vehicle access.

Thank you for your patience and support as we continue delivering these improvements for the community. 🚧

Scarr Street Works Progression 🚧Stage 2 – Final earthworks and trimming activities are currently underway in preparation...
10/07/2026

Scarr Street Works Progression 🚧

Stage 2 – Final earthworks and trimming activities are currently underway in preparation for handover to Auzscott for the upcoming concrete works.

Stage 3 – Demolition works are progressing well across the site. The existing driveway will remain in place until the associated stormwater works commence. Sewer works are scheduled to begin on Monday, with stormwater installation to follow upon completion of the sewer works.

Traffic Management Updates:

Sewer works will commence at the King Street intersection, extending from the Health Precinct through to Access Electronics. Traffic management measures will be in place throughout these works, and motorists and pedestrians are encouraged to follow all signage and directions from traffic controllers. Some temporary changes to access and traffic conditions may be required while these works are undertaken.

Overall, the project continues to progress well, and we appreciate the community's ongoing patience and cooperation.

If you have any questions, please contact us at:
📧 [email protected]

01/07/2026

Scarr Street Works Progression 🚧

Stage 2 – Most of underground works are now complete, with the exception of the crossing in front of Australia Post at the end of Scarr Street. This is expected to be finalised by the end of the week, allowing the road to reopen on the Central Hotel side, with a shoulder closure remaining on the Australia Post side. Final trimming works will commence Monday in preparation for handover to Auzscott for concrete works.

Stage 3 – Following the installation of fencing yesterday (30/06/26), demolition works are scheduled to commence this week. Driveway access will remain open, as previously advised.

Traffic Management Updates:
Due to sewer rework activities, the area near the Central Hotel and Australia Post will be temporarily closed for a few days. This is not expected to
significantly impact traffic, as a nearby turnaround option will remain available.

Overall, the project is progressing well, and we appreciate your continued patience and cooperation.

If you have any questions, please feel free to contact us via email:
[email protected] "

24/06/2026

Scarr Street Works Update 🚧

Stage 2
We’re nearly done with the underground services and are moving into final trimming and prep for handover to Auzscot to start the concrete works.
Due to a redesign, the sewer works in front of the Central Hotel and near the Post Office (end of Scarr Street) will need to be redone.
Traffic controllers will continue to be on site daily to help both pedestrians and vehicles move safely through the area.

Stage 3
From tomorrow (26 June), we’ll be setting up temporary shoulder closures, with fencing and signage in place.
Access to driveways, businesses, and pedestrian paths will remain open.
Please note there will be intermittent road crossing closures while we complete the sewer and stormwater crossings at King Street.

Overall, the project is progressing well, and we really appreciate your patience and cooperation.

If you have any questions, feel free to reach out:
📧 [email protected]
Thanks,

18/06/2026

Works Progression 🚧

Stage 1 – New footpath was opened to the community on 9th June, corner sections currently remain closed with temporary fencing.

Stage 2 – The majority of underground services are nearing completion in stage 2, during the week of 22nd June the temporary fencing will be realigned to a shoulder closure only, re-opening the stage 2 lane to traffic. Once the lane is re-opened the intermitted road crossing closure will be implemented for the completion of the Sheaffe Street end Sewer and Stormwater road crossings.

Stage 3 - Shoulder closure temporary fencing and signage will be implemented on approx. Tuesday 23rd June. Driveway, business and pedestrian access to remain open. Please note that intermitted road crossing closures will be required to complete the King Street Sewer and Stormwater road
crossings.

Overall, the project is progressing well, and we appreciate your ongoing patience and cooperation.

If you have any questions, please feel free to get in touch via email:
[email protected]

10/06/2026

Works Progression 🚧

Stage 1 – Most of the fencing has now been removed and the footpath has been reopened for pedestrian use, except for corner sections where a water main redesign is required and works are still pending.

Stage 2 – The majority of the stormwater works have been completed, except for the crossing in front of Australia Post at the end of Scarr Street. This section required redesign, and rework will be commencing shortly. Over the coming week, fencing will be adjusted to a shoulder closure setup while the stormwater crossing is finalised.

Stage 4 - Works are currently scheduled to commence at the beginning of July.

Traffic Management Updates:
Following the updated sewer design, rework activities will begin. This will require temporary closures around the Central Hotel and Australia Post to allow the works to be completed safely.

Water main, subsoil drainage, and irrigation works are ongoing at Lot A within Stage 2, progressing from Australia Post through to the Police Station.

Overall, the project is moving ahead well, and we appreciate your ongoing patience and cooperation.

If you have any questions, please feel free to get in touch via email:
[email protected]

03/06/2026

🚧Scarr Street Project Updates🚧:

Stage 1 – Auzscot will complete the main concrete works this week, except for both corners where an updated design is required. Once this is resolved, fencing will be relocated and pedestrian access reinstated.

Stage 2 – Following the full closure of Stage 2, good progress has been made on stormwater works, which are now nearing completion. Next week, fencing will be adjusted back to a shoulder closure arrangement while we complete the stormwater crossing and finalise sewer works at the Australia Post end.

Traffic Management Updates:

Following receipt of the updated sewer design, reworks will commence. As a result, areas near the Central Hotel and Australia Post will be closed again to allow completion of these works.

Water main, subsoil, and irrigation works have commenced at Lot A within Stage 2, progressing from Australia Post through to the Police Station.

Overall, works are progressing well, and we thank you for your patience and cooperation.

If you have any questions, please feel free to contact us via email:
[email protected]

22/05/2026

Works Progression 🚧

Stage 1 – Auzscot has been preparing the footpath for pouring this week, with completion expected by the end of next week.

Stage 2 – Stormwater installation (Lot B-in front of the park), along with electrical and irrigation works, has now been completed. Works are progressing into subsoil installation, kerb inlet entry, and preparation for handover to Auzscot for concrete works.

Traffic Management Updates:
• Due to a redesign, works in front of the Central Hotel/Fire Station are currently on hold until further direction is received. As a result, the road closure will remain in place for a little longer.
• A full closure of Stage 2 will be implemented once Stage 3 can be opened to maintain one-lane access at all times.
• Works will commence at Lot A of Stage 2, progressing from Australia Post through to the Police Station.

Overall, works are progressing well, and we thank you for your patience and cooperation.

If you have any questions, please feel free to contact us via email:
[email protected]

The Durack Civil Team

23/04/2026

Durack has exciting news regarding works progression. 🚧

Stage 1 has been handed over to Auzscott, a local subcontractor delivering the concrete works since last Friday. We are very excited to see footpath construction commencing as this stage moves into its final phase.

For Stage 2, stormwater installation is continuing, with excavations reaching depths of approximately 3.2 metres. Searles Plumbing is doing a great job completing these works within a very tight space.

ANZAC Day
Please note there will be no construction works this weekend due to ANZAC Day. Durack Civil is supporting Cloncurry Shire Council by providing traffic management and road closures from 5:00 am to 11:00 am to help ensure a safe and respectful day.
Thank you for your patience and cooperation.

If you have any questions, please feel free to reach out.

The Durack Civil Team

30/03/2026

Exciting news — we’re finally heading into Stage 2! 🚧

With Stage 1 entering its final phase, Auzscott will be taking over for concrete works.

For Stage 2, fencing was installed yesterday for part of the area, and works are planned to commence shortly after Easter.

Following the same approach as Stage 1, works will begin with underground services, including stormwater, water main, comms, electrical and irrigation. This will then be followed by concrete works also undertaken by Auzscott.

Thank you for your ongoing patience and cooperation.

If you have any questions, please feel free to reach out.

The Durack Civil Team

Address

Cloncurry, QLD
4824

Alerts

Be the first to know and let us send you an email when Durack Civil: Scarr Street Revitalisation posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Durack Civil: Scarr Street Revitalisation:

Shortcuts

Share