PROJECT UPDATE | MARION BASKETBALL CENTRE
Richmond Co continues to progress civil and earthworks at the Marion Basketball Centre, working alongside Kennett Builders.
Our team has completed site-wide excavation to natural ground level, with site-won material conditioned, placed and compacted under Level 1 supervision.
Following inclement weather, additional works were undertaken to the building pad to achieve the required site conditions. This included ripping the building pad in preparation for lime stabilisation, followed by the supply, placement and reconditioning of material to revised design levels in preparation for Type A material placement.
Further works included the supply, placement and compaction of PM2 material across the building pad, car park and pavement areas.
With final trimming of the building pad and footing set-downs now complete, the site is ready for concrete footing works to commence.
Another key stage of the project completed by the Richmond Co team.