03/24/2026
NTI, a Norland Company, is halfway through a major industrial materials-handling installation in the lower mainland, and the progress on site has been impressive!
Over the past year our team has been working on the railcar dumping system for a potash expansion project that will move Canadian potash mined in Saskatchewan to the BC coast for export around the world. This system forms the receiving end of the transport chain - where full unit trains arrive and are positioned, indexed, and unloaded efficiently to keep material flowing.
What we've accomplished so far:
āļøInstalled rail support beams and hopper systems
āļøInstalled the vibratory feeders, quadrant gates, and tail end receiving conveyor
āļøErected the dumper assembly building housing all of the equipment
āļøBegan erecting the dust collection system
āļøInstalled the pre-fabricated substation building āļøInstalled the railcar indexer spinebar and rails to extremely tight tolerances
āļøReceived and pre-assembled the indexer staged outside of the assembly building
āļøBegan outfitting the electrical, hydraulic, lubrication, pneumatic, washdown, and vacuum systems
As the general contractor, NTI is coordinating multiple subtrades while self-performing the structural and mechanical installations.
We're excited to move into the next phase of installation and commissioning, building the infrastructure that keeps Canadian trade moving.