07/18/2026
The original layout was divided by load bearing walls throughout. The project was fully engineered prior to demolition, with two W6 steel beams installed to carry the main floor, concealed within the ceiling.
Scope of work:
Structural wall removal and steel installation
Kitchen relocated to the centre of the home
Plumbing, HVAC and electrical rerouted
New powder room
New oak staircase with iron spindles
Wide plank flooring throughout
Timeline: 4 weeks from demolition to completion.
Design: custom cream cabinetry, walnut island, quartz counters and full height backsplash, brass fixtures.