Project Overview | Bath Fire Station, BathWorking in the heart of a historic city always demands careful planning – and ...
10/08/2026

Project Overview | Bath Fire Station, Bath

Working in the heart of a historic city always demands careful planning – and the demolition of the former Bath Fire Station was no exception.

This complex project required the safe removal of asbestos, a full internal soft strip and the controlled demolition of the fire station, all while operating immediately alongside a live ambulance station. Through meticulous planning, robust environmental controls and a safety-first approach, our team successfully cleared the site, ready for the next phase of its redevelopment.

Our latest Project Overview takes a closer look at:
✔️ Careful planning in a live operational environment
✔️ Asbestos removal and enabling works
✔️ Sustainable demolition and material recycling
✔️ Overcoming unexpected site challenges
✔️ Delivering a safe, efficient project for our client

Read the full Project Overview under the Projects page on our website.

It’s not everyday you receive a photo like this 📸A huge thank you to  for sharing this fantastic image from our Bath Fir...
15/07/2026

It’s not everyday you receive a photo like this 📸

A huge thank you to for sharing this fantastic image from our Bath Fire Station Project. We’re proud to have played a part in preparing the site for its next chapter 🚒

We are looking for a HGV Driver (Hook Loader) DriverFull-time EmployeePermanent£ Discussed upon application Benefits- An...
09/07/2026

We are looking for a HGV Driver (Hook Loader) Driver

Full-time Employee
Permanent
£ Discussed upon application

Benefits
- Annual Leave
- Company Pension
- Free on-site parking

We are seeking a professional and reliable HGV (C +E) hook lift driver with draw-bar experience. This role is ideal for an experienced driver who takes pride in operating safely and maintaining high standards. Our works are based across the South of England and Wales and therefore nights out are required where workload dictates. The ideal candidate will be highly organised, a strong communicator, and work well both in a team and independently.

Responsibilities
- Operate one of our RORO vehicles in an safe and efficient manner, in line with company requirements
- Complete daily vehicle checks, reporting any defects ensuing that your vehicle is roadworthy and presentable to Company standards
- Comply with all legislation including drivers hours and highway regulations
- Complete and maintain paperwork in line with company procedures

Qualifications and experience
- Must have RoRo and drawbar experience
- Full driving licence valid in the UK, with no more than 6 points on licence
- HGV (C+E) driving licence
- Valid driver CPC card
- Valid digital tachograph card

If you are interested in the above role, please send your CV to [email protected] or call our office on 01761 452391 and speak to Rachael to discuss further.

**NO AGENCIES PLEASE**

24/06/2026

Progress on site at Bath Fire Station 📍 

Our team continues to advance the demolition works, with a strong focus on safety, planning, and efficient delivery throughout each stage of the project.

🎥 Take a look at the latest footage from site

15/06/2026

https://www.facebook.com/share/r/1DxqLibhK9/?mibextid=wwXIfr

Bath Fire Station was a landmark building with a long history in the city, and we were proud to be entrusted with delivering the enabling works and demolition package on this significant project.

Our team carried out a full programme of works, including asbestos removal, soft strip, demolition, ground remediation and the creation of a piling mat, all within a sensitive city-centre environment.

Projects involving historic buildings require far more than simply taking structures down. They demand careful planning, extensive surveys, robust environmental controls and a highly experienced team capable of protecting neighbouring properties, local businesses and the wider community throughout the process.

While buildings often hold a special place in the hearts of local residents, there are occasions when redevelopment becomes necessary to meet modern safety standards, operational requirements and the future needs of a city. Our role is to ensure that process is carried out safely, responsibly and with the utmost respect for both the site and its surroundings.

We would like to thank everyone involved in the successful delivery of this project.

Bath Fire Station coming down
10/06/2026

Bath Fire Station coming down

A selection of photos from our near-complete project in Caerleon, South Wales.Over the past 12 weeks, we’ve carefully so...
06/05/2026

A selection of photos from our near-complete project in Caerleon, South Wales.

Over the past 12 weeks, we’ve carefully soft stripped, cleared and demolished part of a live school environment—navigating ecology, archaeology and licensed asbestos works, all while maintaining programme.

Another successful project delivered, and a pleasure to be working with a valued repeat client.

A selection of photos from our near-complete project in Caerleon, South Wales.Over the past 12 weeks, we’ve carefully so...
06/05/2026

A selection of photos from our near-complete project in Caerleon, South Wales.

Over the past 12 weeks, we’ve carefully soft stripped, cleared and demolished part of a live school environment—navigating ecology, archaeology and licensed asbestos works, all while maintaining programme.

Another successful project delivered, and a pleasure to be working with a valued repeat client.

Works nearing completion at Passage Street. The traffic management system has been stripped with the road and pavements ...
27/04/2026

Works nearing completion at Passage Street. The traffic management system has been stripped with the road and pavements thoroughly cleaned.

Scaffold complete in the centre of Cheltenham where we’re removing the link bridge between Cavendish House and Regent Ar...
13/04/2026

Scaffold complete in the centre of Cheltenham where we’re removing the link bridge between Cavendish House and Regent Arcade. Working to a tight programme and within a particularly sensitive environment, the bridge will be removed using a combination of dismantling and remote demolition methods.

We have maintained vehicular and pedestrian access to either side of the bridge throughout, causing minimal disruption to local residents and businesses.

Address

Bristol
BS396UU

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm
Friday 9am - 5pm

Telephone

+441761452391

Alerts

Be the first to know and let us send you an email when Weaver Demolition posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Weaver Demolition:

Shortcuts

Share