24/03/2026
Just wanted to share a quick update on one of our ongoing projects for Caterfood (South West) Ltd., who supply frozen food across Devon.
Their old drive-in freezer had cracked and lifted from frost, so it was time for a new one... We’ve been managing the whole project as principal contractor: coordinating different companies and making sure everything runs smoothly.
So far we’ve:
-Taken out the old freezer and cleared the site;
-Cut up the old concrete and removed it;
-Excavated soft areas and installed land drainage;
-Poured a new concrete pad for the freezer;
-Started building the walls, which will include insulation, a heating pad, and another concrete floor inside.
It’s great seeing it all come together, and it’ll be a strong, durable freezer ready for years of use. 🫡
Here's more detail about the project: https://leysltd.co.uk/2026/03/24/transforming-caterfoods-drive-in-freezer-paignton/