Sanquhar II Wind Farm

Sanquhar II Wind Farm Providing updates on abnormal load deliveries for Sanquhar II Wind Farm, a 44-turbine project within Dumfries & Galloway and East Ayrshire.

Blade lifter deliveries are scheduled to begin on Monday 8th June.The convoy is due to depart from the transfer area nor...
04/06/2026

Blade lifter deliveries are scheduled to begin on Monday 8th June.

The convoy is due to depart from the transfer area north of New Cumnock at 9:30am, before travelling through New Cumnock along the A76 towards Kirkconnel.

The convoy will then turn right down the C125n and travel to the site entrance. Please be aware that delivery schedules may change at short notice due to weather conditions.

We'll share any updates and a live tracking link on this page, and via our WhatsApp channel, on Monday morning.

Further delivery dates will be confirmed in due course.

Stay Updated on Blade Deliveries – Join Our WhatsApp ChannelAs blade deliveries begin for the Sanquhar II Wind Farm proj...
02/06/2026

Stay Updated on Blade Deliveries – Join Our WhatsApp Channel

As blade deliveries begin for the Sanquhar II Wind Farm project, we encourage local residents to join our dedicated WhatsApp channel for live updates.

The channel will provide timely information on delivery schedules, traffic management arrangements, and any important notices related to the transport of turbine components through the area.

πŸ‘‰ Join the WhatsApp channel here:
https://whatsapp.com/channel/0029VbCEqtvJUM2VYl2Npe2w

By subscribing, you'll receive updates directly to your phone and stay informed throughout the delivery period.

Thank you for your patience and cooperation as we progress with the construction of Sanquhar II Wind Farm.

Follow Sanquhar II Wind Farm's WhatsApp channel. Providing updates on abnormal load deliveries for Sanquhar II Wind Farm, a 44-turbine project within Dumfries & Galloway and East Ayrshire.. Join 24 followers for the latest updates.

CWP Energy expects blade deliveries to commence for Sanquhar II Wind Farm in early June, and we hope this page will help...
26/05/2026

CWP Energy expects blade deliveries to commence for Sanquhar II Wind Farm in early June, and we hope this page will help keep the community informed throughout the delivery phase.

From port to the transfer area in New Cumnock, blades will be transported on a standard trailer, with these deliveries taking place at night. From the transfer point to site, turbine blades will be transported using a blade lift trailer. The blade lift raises the blade up to an angle of up to 60-degrees, allowing it to navigate tighter corners that would not otherwise be possible. The route the blade lift will be taking can be seen here - https://www.sanquhar2windfarm.co.uk/abnormal-load-deliveries

As agreed with East Ayrshire Council and Dumfries and Galloway Council, the first two weeks of movements will take place during the day, between 9:30am and 3:00pm. Following this period, deliveries will move to evenings, with deliveries departing the transfer point from 6:30pm onwards.

All deliveries will take place under police es**rt and some delays may occur. There will be designated points along the route where blades may be stopped to allow traffic to pass, this will be at the discretion of the police.

This page will provide weekly updates on expected deliveries, along with links to track the location of the blades to allow your journeys to be planned. Deliveries can be cancelled at last minute due to weather conditions and that information will also be posted here.

Updates will also be shared via our Sanquhar II WhatsApp channel, which you can join here: https://whatsapp.com/channel/0029VbCEqtvJUM2VYl2Npe2w

If you have any questions or require further information, please contact us on:
Email: [email protected]
Phone: 01928 734544

Wind turbine component deliveries are scheduled to take place this week for Sanquhar II Wind Farm. We expect to deliveries to take place from Monday 18th- Thursday 21stMay. The deliveries will be leaving King George V Port in Glasgow at approximately 7pm each day and are due onsite by 1:00am.

Wind turbine component deliveries are scheduled to take place this week for Sanquhar II Wind Farm. We expect to deliveri...
18/05/2026

Wind turbine component deliveries are scheduled to take place this week for Sanquhar II Wind Farm. We expect to deliveries to take place from Monday 18th - Thursday 21st May. The deliveries will be leaving King George V Port in Glasgow at approximately 7pm each day and are due onsite by 1:00am.

The route the components will be following can be found here - https://sanquhar2windfarm.co.uk/abnormal-load-deliveries

Please note that traffic movements are subject to change due to operational delays and police availability.

Wind turbine component deliveries are scheduled to take place this week for Sanquhar II Wind Farm. We expect to deliveries to take place from Monday 18th- Thursday 21stMay. The deliveries will be leaving King George V Port in Glasgow at approximately 7pm each day and are due onsite by 1:00am.

A beautiful sunny day in Scotland and great progress on site β˜€οΈMore turbine towers successfully delivered on site, as th...
09/04/2026

A beautiful sunny day in Scotland and great progress on site β˜€οΈ

More turbine towers successfully delivered on site, as the project continues to take shape across the hills.

Seeing these components arrive really brings the scale of the development to life, and highlights the progress being made towards delivering clean, renewable energy.

A great view of activity at King George V Dock.Phase 1 wind turbine towers have now been successfully delivered, with so...
02/04/2026

A great view of activity at King George V Dock.

Phase 1 wind turbine towers have now been successfully delivered, with some already transported onwards to site at Sanquhar.

This snapshot captures the scale of operations at the port as we continue moving key components through the next stage of the project.

A big thanks to everyone involved in coordinating and handling these deliveries β€” another important step forward for renewable energy in the region. 🌍

26/03/2026

We’d like to inform the local community about upcoming turbine tower deliveries for Sanquhar II Wind Farm.

Deliveries will take place Monday to Thursday, following the route and estimated timings below:

β€’ Departing King George V Dock, Glasgow – 7:30pm
β€’ Passing through New Cumnock – 11:00pm
β€’ Arriving on site – Midnight

Please note these times are approximate and may vary depending on police availability and es**rt requirements.

Thank you for your patience and understanding while these deliveries are carried out safely.

We will keep you updated with the delivery timings as they progress.

24/03/2026

Delivery Update - Sanquhar II Wind Farm

We would like to inform our community that turbine deliveries are scheduled to take place Monday to Thursday overnight over the coming weeks.

Please note that all deliveries are subject to police availability.

We apologise for any inconvenience caused and appreciate your understanding.

Thank you,

CWP Energy