👷‍♂️Part 7 Steel deck installation on the 3rd floor has been completed, and concrete pouring has already been carried ou...
03/05/2026

👷‍♂️Part 7

Steel deck installation on the 3rd floor has been completed, and concrete pouring has already been carried out. On the 2nd floor, CHB masonry wall laying has also commenced.

Trivia: A steel deck serves as permanent formwork and reinforcement support for the slab, helping accelerate the construction timeline while enhancing the structural system.

Our team is here to help make your dream home a reality! 🏡💫

Got questions? Just send us a message directly.

Our services include:

📌Demolition (removing old buildings or structures)
📌House planning (layout and design ideas)
📌House design (interior and exterior look)
📌Full construction (we build from start to finish)
📌Renovation (updating or fixing existing homes)
📌Electrical and plumbing work
📌Roofing (installing or repairing your roof)
📌Flooring and tiling
📌Painting and finishing touches
📌Help with building permits
📌Project supervision (we manage the whole process)

We’re ready to guide you every step of the way. Message us to get started! 🛠️







👷PART 6The beams for the third floor have already been constructed. After the concrete pouring of the beams, a steel dec...
21/04/2026

👷PART 6

The beams for the third floor have already been constructed. After the concrete pouring of the beams, a steel deck slab system was installed, followed by the placement of electrical conduit rough-ins** to serve as pathways for future wiring installations.

Trivia:
Installing electrical conduits before slab casting, commonly called embedded conduit rough-in is critical because it prevents the need for cutting or drilling hardened concrete later. This preserves the structural integrity of the slab, reduces labor costs, and ensures proper alignment of electrical systems. In structural engineering practice, avoiding post-installed penetrations helps maintain the designed load distribution and minimizes potential cracking or weakening of the concrete.

Our team is here to help make your dream home a reality! 🏡💫

Got questions? Just send us a message directly.

Our services include:

📌Demolition (removing old buildings or structures)
📌House planning (layout and design ideas)
📌House design (interior and exterior look)
📌Full construction (we build from start to finish)
📌Renovation (updating or fixing existing homes)
📌Electrical and plumbing work
📌Roofing (installing or repairing your roof)
📌Flooring and tiling
📌Painting and finishing touches
📌Help with building permits
📌Project supervision (we manage the whole process)

We’re ready to guide you every step of the way. Message us to get started! 🛠️

👷Part 5Following the casting and initial curing of the second-floor slab, column formwork for the third level was prompt...
04/04/2026

👷Part 5

Following the casting and initial curing of the second-floor slab, column formwork for the third level was promptly erected.

Trivia:
In structural engineering, starting column formwork soon after slab curing is common in fast-track construction. However, engineers must ensure the slab has reached adequate early strength (often around 70% of its design strength) to safely support additional loads from workers, materials, and formwork. This process is closely tied to the concept of construction staging, which ensures each structural element can handle loads during every phase not just in the final design.

👷Part 4 The second-floor beam was properly formed and subsequently poured with concrete, ensuring structural integrity a...
25/03/2026

👷Part 4

The second-floor beam was properly formed and subsequently poured with concrete, ensuring structural integrity and alignment with design specifications.

Trivia:

In structural engineering, the process of “pouring” concrete into a formed beam is part of what’s called cast-in-place concrete construction. One critical concept here is curing, after pouring, concrete must retain adequate moisture, temperature, and time to achieve its desired strength. Improper curing can significantly reduce the beam’s load-bearing capacity, even if the mix design is correct.

👷PART 3Rebar installation for the foundation was carried out, along with the simultaneous layout and installation of the...
21/03/2026

👷PART 3

Rebar installation for the foundation was carried out, along with the simultaneous layout and installation of the water supply line and sanitary drainage line. A polyethylene sheet (moisture/v***r barrier) was also installed.

Why these are important: Rebar provides tensile strength to concrete, preventing cracking and structural failure. Proper installation of water supply and sanitary lines ensures efficient serviceability and avoids costly rework or leaks after concreting. The polyethylene v***r barrier minimizes moisture intrusion, protecting the slab from deterioration, reducing mold risk, and helping preserve the integrity of both the concrete and embedded reinforcement.

Trivia: Prior to installing the polyethylene sheet for slab-on-grade construction, a granular base layer (gravel bedding) is typically placed and compacted to improve drainage and load distribution. This is followed by the application of a soil termiticide to mitigate termite infestation risks before placing the v***r barrier. In some Filipino construction practices, a traditional ritual known as “blood offering” (pagpapadugo) is also performed as a cultural belief for safety and good fortune during construction.

👷PART 2Excavation for footing and casting of reinforced concrete columns and grade beams🔧 Construction Trivia!🏗️Did you ...
19/03/2026

👷PART 2

Excavation for footing and casting of reinforced concrete columns and grade beams

🔧 Construction Trivia!🏗️

Did you know? Before a building rises, engineers first perform foundation excavation, to prepare the ground. Then, they construct, reinforced concrete columns, and grade beams. These act like the skeleton of the structure, distributing loads and keeping everything stable.

👉Fun fact: Grade beams help connect columns and prevent uneven settling, especially on weaker soil.

Engineering isn’t just building up, it starts by digging down!

👷PART 1Mobilization and Excavation works for the septic tank. Excavation of a septic tank involves the removal of soil t...
18/03/2026

👷PART 1

Mobilization and Excavation works for the septic tank.

Excavation of a septic tank involves the removal of soil to create a pit of the required dimensions and depth, in accordance with the design plans. The work includes setting out the location, clearing the area, digging to the specified elevation, and ensuring stable side slopes or providing shoring if necessary. The excavation is carried out carefully to avoid over-digging and to maintain proper alignment and level, preparing the site for the placement and construction of the septic tank structure.

JNI Construction at your service.Planning the roofing system for your dream home? Let our team handle it with precision ...
15/03/2026

JNI Construction at your service.

Planning the roofing system for your dream home? Let our team handle it with precision and quality workmanship. At JNI Construction, we focus on proper installation, durable materials, and structural reliability to ensure your roof is built to last.

Send us a DM for inquiries and quotations. Let’s build your home with engineering you can trust.

Proposed: 2- Storey W/ Roofdeck Duplex HouseProject Location: Las Piñas BF ResortThank you for choosing JNI our dear cli...
15/03/2026

Proposed: 2- Storey W/ Roofdeck Duplex House
Project Location: Las Piñas BF Resort

Thank you for choosing JNI our dear client🥰

Our team is here to help make your dream home a reality! 🏡💫

Got questions? Just send us a message directly.

Our services include:

📌Demolition (removing old buildings or structures)
📌House planning (layout and design ideas)
📌House design (interior and exterior look)
📌Full construction (we build from start to finish)
📌Renovation (updating or fixing existing homes)
📌Electrical and plumbing work
📌Roofing (installing or repairing your roof)
📌Flooring and tiling
📌Painting and finishing touches
📌Help with building permits
📌Project supervision (we manage the whole process)

We’re ready to guide you every step of the way. Message us to get started! 🛠️

GROUND BREAKING Project Proposed: 4- Storey Residential HouseProject Location: Dasmariñas City CaviteDate: May 03 2025Th...
06/06/2025

GROUND BREAKING

Project Proposed: 4- Storey Residential House
Project Location: Dasmariñas City Cavite
Date: May 03 2025

Thank you for choosing JNI our dear client🥰

Our team is here to help make your dream home a reality! 🏡💫

Got questions? Just send us a message directly.

Our services include:

📌Demolition (removing old buildings or structures)
📌House planning (layout and design ideas)
📌House design (interior and exterior look)
📌Full construction (we build from start to finish)
📌Renovation (updating or fixing existing homes)
📌Electrical and plumbing work
📌Roofing (installing or repairing your roof)
📌Flooring and tiling
📌Painting and finishing touches
📌Help with building permits
📌Project supervision (we manage the whole process)

We’re ready to guide you every step of the way. Message us to get started! 🛠️

Address

Imus
4103

Alerts

Be the first to know and let us send you an email when JNI Construction Opc posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to JNI Construction Opc:

Share