Philkonstrak Development Corporation

Philkonstrak Development Corporation The professional staff at PDC has over 30 combined years of design, engineering and construction experience.

About Philkonstrak Development Corporation
Philkonstrak Development Corporation (PDC) is a private construction firm registered in the Securities Exchange Commission (SEC) on August 2006 with SEC Registration No: CS200629243. Vision:

PDC envisions being the most developed, progressive and leading construction firm globally with the highest construction category, attaining the best quality of work

manship having stable human, physical and financial resources. CONSTRUCTION SERVICES

We specialize in design/build construction, providing single-source responsibility for the entire construction process. Our management team handles every phase and variable of the project - from architectural and engineering services thru construction administration. In the process, we will manage site selection, soil testing, environmental analysis, tax abatements and obtain the required governmental approvals and permits. We believe this process offers our clients substantial savings in time and money, without compromise design/build firm, a construction management team or a general contractor – PDC has the capabilities to serve your building needs. We also excel in the area of construction management. This variant to the traditional construction approach permits an owner to be a more interactive participant in the construction process without sacrificing time, quality or value. Whether your objective is to utilize the services of an experienced

Philkonstrak Development Corporation is pleased to announce Mr. Pergen S. Geotina as the company’s Pollution Control Off...
26/05/2026

Philkonstrak Development Corporation is pleased to announce Mr. Pergen S. Geotina as the company’s Pollution Control Officer (PCO).

As part of our commitment to environmental responsibility and regulatory compliance, Mr. Geotina will oversee and coordinate the company’s environmental management programs, monitoring activities, compliance requirements, and related initiatives.

We look forward to his valuable contribution in promoting sustainable and responsible operations for the company.

Please join us in welcoming and congratulating Mr. Geotina on his new role.

Project Update Continuous progress on-site despite project suspension. Structural works are ongoing with steady advancem...
21/05/2026

Project Update

Continuous progress on-site despite project suspension. Structural works are ongoing with steady advancement on tie beams, footings, columns, and cistern tank wall activities.

Planned: 9.08% (Currently Suspended)
Actual: 16.63% (Considered VO Quantities w/ Original Timeline)
Variance: +7.55%

Activities:

• Concrete Pouring of Cistern Tank Wall
• Installation of Runners for Tie Beams
• Fabrication of Rebars for Tie Beam
• RSB Installation for Tie Beams
• Continuation of Fabrication and Installation of RSB for Footings and Columns

09/05/2026

This Mother’s Day, PHILKONSTRAK Development Corporation proudly honors and celebrates all mothers, grandmothers, wives, and mother figures whose love, strength, and sacrifices continue to inspire us every day.

Mothers are the foundation of every family and community. Their unwavering dedication, compassion, and resilience shape lives and build brighter futures for generations to come.

To all the mothers within the PHILKONSTRAK family, we extend our heartfelt gratitude for your hard work, care, and invaluable contributions both at home and in the workplace. Your commitment and perseverance are truly appreciated.

May this special day remind you how deeply valued and cherished you are—not only today, but every day.

From all of us at PHILKONSTRAK Development Corporation,
Happy Mother’s Day!

📣 ANNOUNCEMENTGood day, Philkonstrak Development Corporation Team!We are pleased to announce the appointment of Mr. Robe...
06/05/2026

📣 ANNOUNCEMENT

Good day, Philkonstrak Development Corporation Team!

We are pleased to announce the appointment of Mr. Roberto C. Mejares, Jr. as our new Property Management Development Operations Officer II, coming from his previous role as Project-In-Charge assigned in Dalaguete.

His experience in project supervision and site operations will be a great asset to our Property Management Division as we continue to strengthen our preventive and repair/maintenance programs across all projects.

Let us all extend our warm congratulations and full support as he takes on this new responsibility within the company.

Welcome and congratulations, Sir Roberto!

📊 PROJECT UPDATE | IMPROVEMENT WORKS – PARAIZZO DE MARIA RESORT📍 Project Code: 5-009🌤️ Weather Condition: SunnyACCOMPLIS...
05/05/2026

📊 PROJECT UPDATE | IMPROVEMENT WORKS – PARAIZZO DE MARIA RESORT

📍 Project Code: 5-009
🌤️ Weather Condition: Sunny

ACCOMPLISHMENT (Additional Works)

• Wall painting works (balusters & slab area after planter box removal at backside of guest house) – 99% completion (emulsion paint remaining)
• Concrete slab works – 100% completed
• Grass paver block – awaiting materials
• Wall painting (backside of Sto. Niño & corner of guest building) – 100% completed
• Wall painting (lower side of steel railings front of Sto. Niño & back of family guest house) – ongoing, awaiting structural design for slope protection

ONGOING ACTIVITIES

• Application of tile grout for 600x600 tiles at Sto. Niño & border line painting (1 worker)
• Second coating for wall railings front of Sto. Niño (1 worker)
• Painting works at corner side of Sto. Niño (1 worker)
• Concrete pouring for floor slab at back of guest house (2 workers)
• Hauling of excavated materials & removal of formworks near gazebo slab (4 workers)
• General housekeeping activities (all workers)

📌 Continuous improvement works are ongoing to ensure quality finishes and timely completion of remaining punch list items.

PROJECT UPDATEWork progress is steadily moving forward despite suspension on planned timeline. Current accomplishments a...
05/05/2026

PROJECT UPDATE

Work progress is steadily moving forward despite suspension on planned timeline. Current accomplishments already exceeded expectations through VO scope adjustments.

🔹 Planned Progress: 9.08% (Suspended)
🔹 Actual Progress: 14.34% (Incl. VO Quantities w/ Original Timeline)
🔹 Variance: +5.26%

📌 Ongoing Works:
• Cutting of Tree (3/3)
• Installation of CHB @ Septic Tank
• Installation of Forms for Cistern Tank Wall
• Manual Excavation for Tie Beams

💪 Continuous progress on site. Safety and quality remain our top priority.

PROJECT UPDATEWe’re making steady progress on-site with our pipeline installation works 💪✅ Planned: 20.25%✅ Actual: 22.7...
05/05/2026

PROJECT UPDATE

We’re making steady progress on-site with our pipeline installation works 💪

✅ Planned: 20.25%
✅ Actual: 22.75%
📈 Variance: +2.50%

📍 Key Accomplishments:
• Ongoing installation of 8" Spiral Welded Pipe @ Maangtud
• Completed excavation of 4 joints
• Continuous hauling and pipe laying operations

⚙️ Progress Highlights:
• 160mm OD Pipes – nearing completion
• Ongoing installation across 110mm, 90mm, and 63mm lines

⚠️ Challenges Encountered:
• Insufficient fuel supply
• Rainy weather affecting site access road
• Limited generator for welding works
• Boom truck hydraulic leak requiring repair and inspection

Despite the challenges, the team continues to push forward to meet targets 💯

Today, we honor the hardworking men and women whose dedication, skill, and perseverance help build progress every day.Th...
30/04/2026

Today, we honor the hardworking men and women whose dedication, skill, and perseverance help build progress every day.

This Labor Day, Philkonstrak Development Corporation proudly celebrates all workers who continue to shape communities, strengthen industries, and inspire excellence through their commitment.

Your hard work is the foundation of success, and your contributions are truly valued.

Happy Labor Day!
Salute to every worker who builds a better tomorrow.

We are proud to share the successful conduct of our Blood Donation Activity held last April 17, 2026. ❤️🩸Through the col...
20/04/2026

We are proud to share the successful conduct of our Blood Donation Activity held last April 17, 2026. ❤️🩸

Through the collective efforts of our dedicated volunteers, partners, and generous donors, we were able to make a meaningful impact in helping save lives. Your willingness to give a part of yourself for others truly embodies the spirit of compassion and community.

We extend our heartfelt gratitude to our Top Management for their unwavering support, to the organizing team from the Ims Div for their hard work and dedication, and to our partner, the Philippine Red Cross, for their invaluable collaboration in making this initiative possible.

Thank you as well to everyone who participated and supported this activity. Your contribution goes beyond what words can express—it brings hope and a second chance to those in need.

Let us continue to work together in building a culture of care and kindness. Until our next life-saving activity!

📌 Project Update25-009 – Improvement of Paraizzo de Maria Resort☀️ Weather: Sunny🔨 Accomplishments:• Gazebo & Trellis (a...
13/04/2026

📌 Project Update
25-009 – Improvement of Paraizzo de Maria Resort

☀️ Weather: Sunny

🔨 Accomplishments:
• Gazebo & Trellis (as per contract: 100% – paint not included)
• Gazebo & Trellis (actual: 99%)
• Wall painting (99.5%)
• Sto. Niño railings (100%)
• Sto. Niño walls (1st coat applied)

⚙️ Ongoing Activities:

Second coat & emulsion paint – gazebo columns
Apply hardener & sanding – concrete gutter
Concrete pouring (pebbles flooring) – gazebo
Concrete pouring – gutter pedestal
Installation of chandelier
Second coat – grotto wall
Second coat & emulsion paint – walling side of tables
First coat – stair entrance
Semi-gloss painting – grotto garden

📌 Project UpdateConstruction of GCGMMC BUCAS Center – Municipality of Trinidad, BoholPlanned: 9.08% (Currently Suspended...
13/04/2026

📌 Project Update
Construction of GCGMMC BUCAS Center – Municipality of Trinidad, Bohol

Planned: 9.08% (Currently Suspended)
Actual: 13.23% (Based on Original Contract – For Approval Variation)
Variance: +4.15%

🔨 Activities:
• Clearing and installation of forms for footing
• Concrete pouring for footing (17/49)

Address

Door 3, MGR Bldg, Sunrise Village, Apitong Street, Ext, Cebu City
Cebu
6000

Opening Hours

Monday 7:30am - 5:30am
Tuesday 7:30am - 5:30am
Wednesday 7:30am - 5:30am
Thursday 7:30am - 5:30am
Friday 7:30am - 5:30am
Saturday 8am - 5:30am

Telephone

+639233043498

Alerts

Be the first to know and let us send you an email when Philkonstrak Development Corporation posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Philkonstrak Development Corporation:

Share