18/05/2025
TPLEx Extension Details as of May 15, 2025
Source: From the Sangguniang Panlalawigan Council Meeting on TPLEx last May 15, 2025 https://web.facebook.com/share/v/1AjdT2e1PM/
Total Length: 57.4km
Segment 1: Rosario - Tubao 19.2km
Segment 2: Tubao - Bauang 22.2 km
Segment 3: Bauang - San Juan 16.03 km
Number of Lanes: 4
INTERCHANGES:
Rosario
Tubao
Bauang
San Fernando
San Juan
From Representative from San Miguel Corporation - the Original Proponent and the winning developer of the TPLEx Extension project (summarized):
1. The final alignment has been submitted to the DPWH for Review.
2. The preparation of Final Design Plan (FDP) is ongoing, which is targeted to be completed by July 2025
3. The parcellary study is ongoing to determine the barangays to be affected, and the affected lot owners
4. The parcellary plan will follow after the approval of FDP
=============================================
hmmm nag-iba ang alignment base sa sketch, particularly sa San Juan area... dati hanggang Taboc ito... pero let us wait sa updates nito...