11/08/2026
BOND STREET
DATE 11-AUG-2026
* Tower A & B: Standby generator shifted to the new platform at the back side. Internal painting work at the 7th typical floor.
* Tower B: Max Bachat-side elevation painting work.
* Tower C: Internal plaster work at the 3rd typical floor. Shuttering and steel binding work for the 7th typical floor partial slab.
* Tower D: Block making work at the rooftop.
* Tower E: Shuttering work for 7th typical floor Part B super columns. Lift steel binding work. Shop painting work.