27/09/2026

BOND STREET
DATE 27-SEP-2026

* Tower A & B: Main power supply panel and lift machine room dressing work for all amenities. Glass and aluminum window panel fabrication work.
* Tower C: Dismantling and debris cleaning of the old office at the ground floor. Internal plaster work at the 3rd typical floor. Electrical conduit work at the 4th typical floor. 7th typical floor Part B slab shuttering work. Steel shifting work at the 7th typical floor.
* Tower D: Ground-floor shop cleaning work.
* Tower E: 7th typical floor Part B slab shuttering work. 6-inch block shifting to the rooftop for masonry work.

12/09/2026

BOND STREET
DATE 10-SEP-2026

* Tower A & B: Aluminum window installation work at the 7th typical floor. New electric power supply meter installation. Basement ramp cleaning for PCC work.
* Tower B: Elevation painting work.
* Tower C: Cement shifting for plaster work. 3rd typical floor plaster work. 7th typical floor Part B slab shuttering work. Remaining Part C column pouring work at the 7th typical floor.
* Tower D: Rooftop block making work.
* Tower C & D: 12 mm glass panel fixing at Shops No. 53, 63, 64 & 65.
* Tower E: 7th typical floor Part B slab shuttering work. Bond Street Hayat Builders and Developers

05/09/2026

BOND STREET
2ND-SEP-2026

* Tower B: Front elevation painting work.
* Tower A & B: Cleaning of the connecting passage for PCC work.
* Tower C: 7th typical floor Part A slab shuttering removal, sand mound making, and curing work. 3rd typical floor internal plaster work.
* Tower D: 7th floor block making work.
* Tower E: Part B slab shuttering work. Sand and seal-coat shifting for block making at the rooftop and 7th typical floor.
Hayat Builders and Developers Bond Street

30/08/2026

BOND STREET
DATE 29-AUG-2026

* Tower C – 7th Typical Floor (Part A): Slab concrete pouring work completed.

18/08/2026

BOND STREET
DATE 17-AUG-2026

* Bond Street – Tower E, 7th Typical Floor (Part B): Concrete pouring of super columns, lift walls, and shear walls has been completed.

17/08/2026

BOND STREET
DATE 16-AUG-2026

* Tower E – 7th Typical Floor (Part B): Concrete pouring of super columns, lift walls, and shear walls.

Happy Independence Day, Pakistan! πŸ‡΅πŸ‡°βœ¨This 14th August, Hayat Builders & Developers celebrates the spirit of freedom, uni...
13/08/2026

Happy Independence Day, Pakistan! πŸ‡΅πŸ‡°βœ¨

This 14th August, Hayat Builders & Developers celebrates the spirit of freedom, unity, and progress. Together, we continue building dreams, creating landmarks, and shaping a stronger future for Pakistan.

May our beloved country continue to rise with peace, prosperity, and success.

Pakistan Zindabad! πŸ‡΅πŸ‡°

πŸ“ž 0311 1114343
🌐 www.hayatbuilders.net

Hayat Builders and Developers

11/08/2026

BOND STREET
DATE 11-AUG-2026

* Tower A & B: Standby generator shifted to the new platform at the back side. Internal painting work at the 7th typical floor.
* Tower B: Max Bachat-side elevation painting work.
* Tower C: Internal plaster work at the 3rd typical floor. Shuttering and steel binding work for the 7th typical floor partial slab.
* Tower D: Block making work at the rooftop.
* Tower E: Shuttering work for 7th typical floor Part B super columns. Lift steel binding work. Shop painting work.

Hayat Builders and Developers

Call now to connect with business.

Address

London Town Qasimabad
Hyderabad
71000

Website

Alerts

Be the first to know and let us send you an email when Bond Street posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share