27/07/2026
These 70-foot beams headed out early with a pilot car for a project that includes eight beams of this size, making for a challenging delivery and installation from start to finish.
Working within an existing building meant there was no straightforward way in. The roof had to be opened so our crane could lift each beam into place after they were rolled through the structure on the floor.
A lot of planning went into this one, but it’s always rewarding to see everything come together.