FIT-OUT 101 · LANDLORD HANDOVER
The keys come with a floor, not an office.
It happens on a lot of office floors. The ceiling is brand new on the day the keys are handed over, and a few weeks into the fit-out, parts of it are down again.
Nothing has gone wrong. The floor arrived at Category A: ceilings, general lighting, air conditioning and sprinklers laid out in an even grid, finished for an empty room. Once meeting rooms and partitions are drawn in, that grid stops fitting. Ceilings open around the new walls, and outlets and sprinkler heads move to follow the layout.
Below that sits shell and core: structure, façade, lifts, risers, and a raw floor where almost everything is still to be built. Above it, Category B is the tenant’s own layer, with rooms, pantry, reception and furniture built around one team’s way of working.
Many of the questions in the first weeks of a fit-out come from the gap between what was handed over and what the office needs. Buildings don’t all draw that line in the same place.
The label says Category A. The handover specification says what is actually on the floor.