DAY 20 – Gezina, Pretoria Nutec Project Progress  Update✅ Touch-ups remaining✅ Cupboards complete✅ Tiling complete✅ Plum...
03/06/2026

DAY 20 – Gezina, Pretoria Nutec Project Progress Update
✅ Touch-ups remaining
✅ Cupboards complete
✅ Tiling complete
✅ Plumbing complete
✅ Electrical installation complete
✅ Painting complete
🔄 House cleaning in progress
✅ All rubbish and construction waste removed
The project is now in its final stage, with only minor touch-ups and final cleaning remaining before handover. Great progress has been made, and the house is looking ready for completion.

03/06/2026

DAY 20 – Gezina, Pretoria Nutec Project Progress Update
✅ Touch-ups remaining
✅ Cupboards complete
✅ Tiling complete
✅ Plumbing complete
✅ Electrical installation complete
✅ Painting complete
🔄 House cleaning in progress
✅ All rubbish and construction waste removed
The project is now in its final stage, with only minor touch-ups and final cleaning remaining before handover. Great progress has been made, and the house is looking ready for completion.

DAY 12 – Gezina, Pretoria GautengCompleted:Outside painting completeInside painting completeVarnish appliedRemaining wor...
26/05/2026

DAY 12 – Gezina, Pretoria Gauteng
Completed:
Outside painting complete
Inside painting complete
Varnish applied
Remaining work:
Cupboards installation
Tiling
Plumbing & geyser installation
Shower glass installation
Basin installation
Toilet seat installation

Day 6 – Gezina Project 🏡🔨• Outside painting underway — our client selected the colours and we brought the vision to life...
20/05/2026

Day 6 – Gezina Project 🏡🔨
• Outside painting underway — our client selected the colours and we brought the vision to life. 🎨
• Final exterior touches and finishings in progress.
• Ceiling and inside wall installations complete.
• Interior painting officially begins.

19/05/2026

Day 5 Video Progress 🔨🏡
Big progress on site today!
✅ 1st stage plumbing and electrical installation completed inside the walls
✅ Pitched ceiling installation in progress
✅ Rhinoboards fitted for internal wall cladding
✅ Cornice installation between wall and ceiling for a clean finish
✅ Verandah and structural finishing underway
Every step bringing this Nutec home closer to completion. Quality workmanship built to last. 💪🏽

Day 5 🔨🏡Big progress on site today!✅ 1st stage plumbing and electrical installation completed inside the walls✅ Pitched ...
19/05/2026

Day 5 🔨🏡
Big progress on site today!
✅ 1st stage plumbing and electrical installation completed inside the walls
✅ Pitched ceiling installation in progress
✅ Rhinoboards fitted for internal wall cladding
✅ Cornice installation between wall and ceiling for a clean finish
✅ Verandah and structural finishing underway
Every step bringing this Nutec home closer to completion. Quality workmanship built to last. 💪🏽

Day 5 – Gezina, Pretoria Gauteng 🏠🔨Big progress on site today!✅ Chromadek roofing installed✅ Verandah put in place✅ Hous...
18/05/2026

Day 5 – Gezina, Pretoria Gauteng 🏠🔨
Big progress on site today!
✅ Chromadek roofing installed
✅ Verandah put in place
✅ House partitioning completed
✅ Windows and doors installed
The structure is really coming together beautifully. Another strong step toward a modern, durable Nutec home. 💪🏽🏡

17/05/2026

Day 4 – Gezina Nutec House 🏠🔨
A strong home starts with the right structure behind the walls and floors. 👌
✔️ OSB boards installed between the Nutec Shera cladding and RhinoBoard interior walls — adding extra strength, insulation support, and improved durability to the structure.
✔️ Shutterply boards fitted underneath before installing the 22mm Knotty Pine flooring — creating a solid, level base that helps prevent movement and increases the lifespan of the floor.
Quality workmanship from the inside out. 🏡

17/05/2026

Day 4 – Gezina Nutec House 🏠🔨
Progress taking shape step by step.
✔️ Nutec Shera outside cladding installed
✔️ OSB wall installation completed
✔️ Roof trusses erected
Building strong, durable homes with quality workmanship. 👌
Patitioning.

Address

71 Diamant Street Akasia
Akasia
0200

Opening Hours

Monday 08:00 - 17:00
Tuesday 07:30 - 17:00
Wednesday 07:30 - 17:00
Thursday 07:30 - 17:00
Friday 07:30 - 17:00
Saturday 08:00 - 17:00

Telephone

+27651428494

Alerts

Be the first to know and let us send you an email when Val loghomes posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share