08/10/2025
โ Project Update
Progress continues at pace on the Icon SA rooftop. Since our last update, we've wrapped up mounting and panel installation, with 100% of the array now in place.
Over the past two weeks, our teamโs been hard at work pulling cables, mounting inverters, connecting DBs, and laying out the final cable trays across the rooftop. Earth cables are in, DC installation is complete, and AC cables have been pulled and connected.
Communication and control systems are now being wired, including the tech sitter and metering interface. With 90% of cable management complete weโre on track for final testing and commissioning.
Whatโs next? Finishing touches, plugging in strings, and powering upโก
An Emergent Energy Project