$3.09 MILLION IN RECTIFICATION AND COMPLETION COSTS. BUT HOW DO YOU PROVE THE NUMBER?
In *Succar v Dominium Homes Pty Ltd* [2025] NSWSC 183, the Supreme Court of NSW considered a construction dispute involving defective and incomplete building works.
An independent Quantity Surveyor assessed approximately **$3.09 million in rectification and completion costs**, excluding GST.
Following adjustments, including construction price escalation, the Court entered judgment for approximately **$3.76 million**.
The case highlights an important distinction in construction litigation.
**Identifying defective work is one thing. Establishing what it reasonably costs to rectify is another.**
A Quantum Expert's assessment goes well beyond simply putting a price against a schedule of defects.
It involves consideration of:
▪️ The required scope of rectification and completion works
▪️ Measured quantities and construction rates
▪️ Labour, materials and subcontractor costs
▪️ Demolition, access and making good
▪️ Preliminaries, contractor margins and contingencies
▪️ Construction cost escalation where appropriate
And importantly, the figures need to be supported by a clear methodology, reasonable assumptions and evidence that can withstand scrutiny.
For construction lawyers and parties involved in disputes, having the right quantum evidence can make a significant difference when establishing the financial consequences of defective works.
**A building expert identifies what needs fixing. A Quantum Expert assesses what it should reasonably cost.**
At Tate & Sons, we provide independent Quantity Surveying and Quantum Expert Witness services for construction disputes across Australia.
If you need assistance with the quantum side of a construction dispute, please get in touch.