Construction of the NuGrow In-Vessel Composting Facility continues to advance, with the Silverstrand team recently completing the first suspended roof slab pour, placing approximately 280mÂł of concrete.
The facility is being delivered in four structural stages, with each stage comprising a ground slab, Dincel wall installation and concrete infill, tunnel columns, and a suspended roof slab. Completion of the first roof slab marks another significant milestone for the project.👏
With the structural works progressing to programme, the team is also progressing well with the construction of the associated leachate management system.đźš§
Once complete, the facility will feature 12 in-vessel composting tunnels and supporting infrastructure, providing NuGrow with increased processing capacity to support the growing demand for sustainable organics recycling and resource recovery across Southeast Queensland.♻️
Great work by the project team, suppliers and subcontractors who continue to drive this important project forward.