Utility Fusion Services

Utility Fusion Services High Productivity poly welding & fabrication servicing the Civil, Mining, Utility and Energy Industries. Certified to ISO9001, Australia Wide Service.

Friday afternoon vibes on the pipeline....17,500m down, 6500m to go! The team delivering safely in Central QLD
08/05/2026

Friday afternoon vibes on the pipeline....

17,500m down, 6500m to go!

The team delivering safely in Central QLD

After the flooding has dried up, its back to full production up here in Central QLD.  3 x welds crews now onsite to keep...
19/03/2026

After the flooding has dried up, its back to full production up here in Central QLD.

3 x welds crews now onsite to keep mainline welding in front of trenching to complete the 23km infrastructure pipeline.

Rotation No.2 is nearing completion in Miles QLD for Nacap & Arrow Energy.  A long, hot 21 day swing has been executed s...
21/02/2026

Rotation No.2 is nearing completion in Miles QLD for Nacap & Arrow Energy. A long, hot 21 day swing has been executed safely. The entire team has performed an excellent job onsite. Still a long way to go.

Work is well under way on our first project of the year with Nacap and Arrow Energy in Miles QLD. Great way to start the...
21/01/2026

Work is well under way on our first project of the year with Nacap and Arrow Energy in Miles QLD.

Great way to start the year.

We're Hiring. With a large book of upcoming projects, we need more people.
17/11/2025

We're Hiring. With a large book of upcoming projects, we need more people.

Utility Fusion Services is seeking Advanced Poly Welders to join our team in the Surat Basin, QLD. Local and DIDO/FIFO Opportunities available.

After nearly 20 months onsite, Utility Fusion Services have completed the HDPE welding scope undertaken on our water inf...
18/06/2025

After nearly 20 months onsite, Utility Fusion Services have completed the HDPE welding scope undertaken on our water infrastructure project in Central QLD

Tens of thousands of manhours have gone into the stringing, welding, excavation, installation and backfilling of the 900mm and 1200mm pipeline.

Over 220 x 900mm welds and nearly 600 x 1200mm welds were completed by our onsite team, all in accordance with our clients safety, environmental and quality procedures.

Projects of this nature always represent new challenges for our team and clients, however the collaborative approach to the methodology from all members of the onsite engineering and construction teams have contributed greatly to the success of this scope.

We thank our project partners PSAH for ensuring the equipment on this project was always fit for purpose and well maintained.

Address

11 River Cove Place
Helensvale, QLD
4212

Opening Hours

Monday 6am - 5pm
Tuesday 6am - 5pm
Wednesday 6am - 5pm
Thursday 6am - 5pm
Friday 6am - 5pm
Saturday 6am - 5pm
Sunday 6am - 5pm

Telephone

0419368073

Alerts

Be the first to know and let us send you an email when Utility Fusion Services posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Utility Fusion Services:

Share