📍 Progress Update | Main Dam Embankment Road
The drone has been up again, capturing the latest along the Main Dam Embankment Road (MDER) as part of the Argyle Diamond Mine Closure Project.
We have just wrapped up the mudrock placement and compaction across this section, bringing the road up to its required design profile and levels. A solid milestone for this stretch of the works. ✅
Next up, we start loading and hauling growth media (GM) into the area, ready to spread across the completed surfaces as we move into the next stage of rehabilitation.
Step by step, returning this landscape to a safe and stable state. 🌱