20/02/2026
🚧 MRCC Nichols Point Drainage Update
Fifth Street upgrade is now complete ✔️ and the team has moved straight onto the First Street stage.
We’re currently undertaking an under road boring operation, keeping the crew busy and putting in the overtime to keep things moving 💪
🔥 Highpoint Estate:
We’re gearing up for asphalt, with the internal second layer and external third layer now complete, along with all internal footpaths and retention basin ✨
Great progress all round big effort from the boys on site!
Garraway Developments