Mick Mullan Building and Plumbing

Call Directions Website

Mick Mullan Building and Plumbing Mick Mullan Building & Plumbing is a family based business that was established in 2001, and has been servicing the South East region of SA.

Parking has been at a premium this week at Connor and Abi’s house, with multiple trades plying their craft!😃😃Leggo and T...
14/11/2026

Parking has been at a premium this week at Connor and Abi’s house, with multiple trades plying their craft!😃😃

Leggo and Tarkyn finished the stone to the applicable walls so Rads could start the rendering process by pressure cleaning the stone initially, and then getting the base coat on, ahead of the redicote next week!👍👍

Once the guys had finished the stonework, they’ve continued on with the brickwork, smacking it out well, to have the back well on the way to being broken!👊👌

Inside, Zayne and Jas finished the last of the gyprock sanding and cornicing early in the week, making way for the guys from K and B Aston Newman Timbers to deliver the second fix materials ready for Crackers to get stuck into locking the place up, which then allowed Justin from The Tile Place to deliver the tiles!👌👌

Whilst all the was happening, Taylor, Will and Matt were also on site preparing and waterproofing the wet areas ready to begin the tiling itself, with the floors going down straight after getting the tick of approval from Mike doing the mandatory inspections for council!🙌🙌

Just for something a bit different this week, Ty and Elliot decided they wanted to do some more concreting, so it was onto Ben and Sushila’s house to start pouring and finishing sections of path and the alfresco area, and whilst in between concrete pours, boxing and preparing the next areas!😂👍
After finishing the last of the boxing to the driveway, we called on James from Borderline Kerbing on the Trakka to dig out the excess spoil in readiness to be preparing and pouring the last of the paths, then we can pour the driveway Monday and Tuesday next week, when it’s not gunna rain like it did Friday, but we pulled the right chain and didn’t pour!🤔🤞😂

The team from CKK arrived at Stephen and Sophie’s house late this week to start the kitchen install, and remaining cupboards throughout the house!🙌🙌

Between all the cupboards finishing later next week, and the tilers due to return about the same time to grout up the bathroom and ensuite, the splashbacks will also be ready to knock over then!👍👍

Louie’s house is really taking shape now, after Crackers, Langas and Tex erected all the trusses and started on the fascias this week!👍👌
Later next week, the guys from Reilly Bricklaying will be on site to build the double stone dividing wall in readiness for the Speccy’s frames and trusses to begin shortly after!😃😃
But hell, that view is really gunna be something to go to bed with, and wake up too!😍😍

08/11/2026
We’ve had a busy couple of weeks concreting, firstly pouring the Speccy and Louie’s slabs!😃😃Doing a strip footing and bu...
06/11/2026

We’ve had a busy couple of weeks concreting, firstly pouring the Speccy and Louie’s slabs!😃😃

Doing a strip footing and buildup, verses a raft slab, makes a huge difference in the timeline of getting the concrete slab down, thus the seemingly slow progress of the build🤔…….but the payoff in time lost, will come back later and be more beneficial, with the landscaping being a hellava lot easier as the retaining walls that would be required, are essentially built into the house itself!👌👌

But in these two houses case, due to the elevation of the slabs is going to give killer views of the Mount, especially lit up at night time!🙌🙌

After K and B Aston Newman Timbers delivered the frames and trusses to site, Crackers, Langas and Tex stood the frames up, giving even more prospective to how these places are going to look!😍😍

Working between the rainy days, we have finished all the concrete paths etc at Stephen and Sophie’s house externally, whilst inside Mick from Mick Ryan Painting has been in and painted the ceilings and undercoated the walls!😁😁

Crackers, Langas and Tex have all but finished the carpentry second fix and Monday should see CKK installing the kitchen, WIP cupboards and built in robes, so the last of the skirtings can be cut in and Zayne can then also finish off the last of the cornice, ready for the painting to continue!!👍👍

While Will has been busy getting the tiling done on Stephen and Sophie’s, Taylor and Matt have been busy over at Ben and Sushila’s house finishing the waterproofing, then setting out and beginning the floor tiling which will flow through the living area, passage and into the wet areas!👌👌
Therefore we’ve had CKK come in to install the kitchen cupboard bases etc, ready for the tilers to tile around, to not only making installation easier but give a better look!👌👌

Ben and Sushila’s brickwork is all but complete with Leggo just having the brick columns left to finish ahead of giving ...
24/10/2026

Ben and Sushila’s brickwork is all but complete with Leggo just having the brick columns left to finish ahead of giving all the walls an acid wash!👍👍
With the brickwork done, it was time for a cleanup to happen, so Buildpro came to site to collect the brick pallets, and Chris and Lambert from MtG Excavations also arrived to load up and take away a truck full of refuse to Sandyridge for sorting and separating!
With the waste gone, we could then dig the stormwater and water trenches ready for the pipe work to be installed during the next week!😁😁

Inside, Matt has been busy priming and sealing the wet areas ready for waterproofing in the next week, ahead of starting the floor tiling!🙌🙌

Point of interest for the uninitiated to tiling, is that the living areas that are to have floor tiles, will have the same tile that will also run through and into the passage, leading into the bathroom, toilet and laundry, therefore the tiling has to begin in the living areas so as not to break the pattern working into the smaller areas!🤔😬👍

Shep, from K and B Mitre 10, delivered our mesh, plastic etc to the Speccy and Louie’s houses ready for us to lay, before installing the boxing getting the slabs ready to pour come Tuesday!😃🙌
Really looking forward to seeing these houses come to fruition, as the views from the main bedroom at the front of the houses is going to be exceptional , especially at night time!🙌🥰

Taylor, Will and Matt have now finished the tiling at JC and Niyo’s house, and along side Crackers, Langas and Tex being well advanced in the carpentry second fix, we now just wait on the guys from CKK getting to site, to install the kitchen and WIP cupboards!👍👍

Stephen and Sophie’s house keeps moving ahead nicely, looking a hellava lot tidier after having a cleanup with Chris and Lambert again getting rid of a load of refuse, and the pallets to being collected and removed by Buildpro!👌👌

After Ty, Tom and Elliot finished the stormwater and water lines, they continued boxing up the footpaths to have them ready to start pouring later this week!😃😃
Crackers, Langas and Tex have also been busy on site knocking over a fair whack of the soffiting and are ready to move onto the cladding once the last puzzle pieces arrive!🤔🤦‍♂️😂
They too have been moving the internal second fix carpentry along, installing door jambs, hanging doors and installing architraves and skirtings, after Zayne and Jas finished the last of the gyprock flushing and sanding!👍👍

By the end of this week, the wall tiling to the bathroom and ensuite will be completed, leaving only the splashbacks for Will to complete once the guys from CKK arrive to site, to install the kitchen cupboards and WIP, as well as the BIR’s getting the house ready for painting!🙌🙌

Stephen and Sophie’s build continued its progress this week, with all the blockwork completed externally, and the rest o...
17/10/2026

Stephen and Sophie’s build continued its progress this week, with all the blockwork completed externally, and the rest of the gyprock hung inside with Zayne starting the flushing process which should lead to having at all sanded and corniced by the end of next week!👍🙌

The boys from CKK were also on site starting the cupboard installation in the wet areas, so the tiling can continue next week, and will be back to site in a week or so, once Zayne’s completed the flushing of the remaining rooms etc, to go ahead with the BIR’s and kitchen etc fit out!👌👌

The progressive improvements and updates to the rooms at Motel Mount Gambier continued this week with Choices flooring coming in for us, and removing 6 rooms worth of old carpet and laying the new carpet tiles!👍🙌
With a bit of new paint splashed around in the coming weeks should give the rooms a bit of a lift!😁😁

The speccy and Louie’s builds got another step closer to getting the slabs down this week, with Ty, Tom and Elliot smashing out the underfloor plumbing and drains to both houses, and after testing and inspections we had Paul on his trakka come in and backfill the drains ready for the guys to start levelling the pads ready to lay mesh and plastic next week!👌👌

We also had Michael and Dick on site to lay the electrical mains to both jobs as well as Jay to install the Telstra conduits for the NBN connections at a later date!👍👍

Leggo and Tarkyn were able to get back to Ben and Sushila’s house to continue the external brickwork, after Sam from K and B Mitre 10 rang with the good news that they had finally had some off white cement land in store!🙌🙌
Inside, Langas and Tex have fitted the architraves to the windows, installed door jams and starting hanging external and internal doors, to really be getting through the second fixing nicely!👍👍

Matt was also on site getting ahead of the game by starting all the floor preparations for the waterproofing and tiling, and we also had Dollar Curtains come and measure up for the blinds, so we can get the order in prior to the end of October order cutoff time, for the remainder of the year!😬👍

We also had a call from Neal to give a him a hand to help pour and finish a driveway for a job which was the last piece of the puzzle for him to knock over and finish!👍👍

It’s been a bit stop/start at the Speccy and Louie’s in the last fortnight, but busy at the same time!🤔🤷‍♂️😂After waitin...
10/10/2026

It’s been a bit stop/start at the Speccy and Louie’s in the last fortnight, but busy at the same time!🤔🤷‍♂️😂

After waiting for the stone buildups to dry out and strengthen up for a week, we were able to get in and concrete fill the cavities before the long weekend, to again be waiting another week for the curing process to occur, till the end of this week to be able to sand fill the slabs!👍👍
After Chris and Lambert from MtG Excavations had finished filling the slabs, we rolled straight into digging the drains ready for Ty, Tom and Elliot to get cracking on the drains and underfloor pipe work next week!👌👌

Stephen and Sophie’s house will look to be on steroids in the next month, after having multiple factors slowing progress recently, we finally have all the products to site to be able to finish the block work, but moreso the elusive cladding for three walls we needed, to be able to knowingly correctly trim the timber frames ready for the application, to enable the gyprock to continue to these particular external walls!🙌🙌

We were still able to push ahead with the wet areas having Taylor, Will and Matt stuck into laying all the floor tiles ahead of CKK coming to site next week to start the cupboard and vanity installations!

With the rain still making its presence felt, we installed the rainwater tanks and connected all the stormwater lines to them to start filling the tanks, either with the permanent downpipes, or a temporary hookup till the block work and cladding are done!👍👌

Ben and Sushila’s house keeps ticking over, with the bath being installed and framed out, Justin from The Tile Place delivering all the wall and floor tiles ready for the waterproofing and tiling to commence, K and B Aston Newman Timbers delivering all the doors and second fix carpentry materials, allowing Tex to spend a couple of days installing architraves etc to the windows throughout!👍👍

Leggo and Tarkyn hit an obstacle in trying to finish off the brickwork with the inability to source the off white cement we are using in the mortar mix for the brickwork!😬😬

A factory fire has halted production of the product to the market, so now it’s a waiting game until they are up and running again, to be able to finish the job.🤦‍♂️🤦‍♂️

The knock on effect is that we can’t install the downpipes, stormwater and water lines, which in turn means we can’t do concrete footpaths either, and not to mention the inability to complete the soffiting or painting!🤷‍♂️🤷‍♂️

But we will at least keep the inside going unless the melamine supply that the guys at CKK use to make cupboard carcasses runs dry, with restrictions already in place due to a shortage of this product too, due to a couple of factories in Victoria and Queensland ceasing operations last year, and the Western Australian supply restricted due to issues with the rail service for the last 4 months, and the new garden shed Borgs are building for manufacturing of this product, not on line essentially till April next year, kinda makes it all feel like COVID shortages all over again!!😳😳🙄🙄🤦‍♂️🤦‍♂️

Be a builder they said!🤔🤔🤷‍♂️🤷‍♂️🤦‍♂️🤦‍♂️😂😂👍👍

We handed over Bob and Jenny’s beautiful house recently, finalising their relocation to Mount Gambier from Adelaide.☺️☺️...
02/10/2026

We handed over Bob and Jenny’s beautiful house recently, finalising their relocation to Mount Gambier from Adelaide.☺️☺️

In somewhat of a coming home for Jenny, as she was originally a Mt girl who used to hang out with her gal pals here, one of which ended up marrying one of my cousins, which probably helped plot the course to end up building with us!🤔🙌

In what is quite a long story, but condensed, essentially I was working on a Saturday morning at the Spec home in Montbretia crt at that time, which we were finishing off to put on the market, when Bob and Jenny pulled up whilst looking around!🤔

After a chat, then looking through the house and loving it, we then started working through the process of changing the plan layout in the following weeks, to achieve the desired functionality and how they envisioned it to be, to suit their needs!🙌🙌

This meant adding in extra bedrooms, a study and making the alfresco into possibly the largest cracking alfresco area we’ve seen!😍😍

Plan done, quote done and accepted, we continued to move through the process!👍👍
It was at this point we hit a bit of a speed bump in the energy efficiency rating requirements, as because the house has a verandah virtually all the way around the house, it posed a problem being able to achieve the 7 star requirement!😬😬
We knew about the site being an M class soil classification, requiring an engineers slab design prior to contracts, so that was all quoted and accounted for!👌👌

But this 7 star rating issue, was proving to be very problematic!🤦‍♂️🤦‍♂️

Even with upgrades to double glazing, foil back insulation under the roof sheeting, R6.0 insulation to the ceiling, R2.5 HD to the walls and underslab insulation under the concrete,(probably about $30-40K in costs)we still couldn’t achieve the 7 star requirements!!😳😳

The talk of having to change the plan, making the windows smaller, removing the verandah etc to try to conform to the requirements, wasn’t what anyone wanted to do!🫣🫣

Fast forward to receiving results from a somewhat left field way of testing a houses air permeability, it was kinda like taking a throw at the stumps and hoping🤞🤞, we ended up receiving great results!😃😃

These results in turn, were applied to Bob and Jenny’s house plan, of which couldn’t achieve the 7 star efficiency previously, but with the results we achieved through testing, now all the $30K plus upgrades (that didn’t get us across the line anyway) were removed and the only upgrades required were R5.0 ceiling insulation and R2.5 to the external walls, in conjunction with the solar system that Bob and Jenny wanted anyway!🙌🙌
Therefore making savings of around the $30K on their house alone, and being fully compliant!😁😁
And fortunately these results can be applied to all builds we do going forward,(of which we have just had our renewal testing done and smashed it once again)which is a huge saving to our future customers and home owners!👌👌

But I digress, back to Bob and Jenny’s cracking house, and what a pearler it is too!😃😃
They may have based it on the speccy at the time, but certainly added their spin to it, creating a beautiful build!😍😍

Not only have they created a great home, but were great people to deal with, even with the distance and travelling required, nothing was to much trouble to sort out, even if it meant a day trip here and there!🙏🙏

And they also hit the ground running after moving in, getting fencing up, and sorting the landscaping etc of which we are back to site currently, helping with some shed and bird avery concrete slabs, whilst also excavating some areas ready for retaining walls and a few other jobs ahead too!😁😁
It’s nice to see the progress you guys are making in quick time, and you’ll have grass growing in no time!🙌🙌

Congratulations on your beautiful home!☺️☺️

Both the spec and Louie’s houses have made significant progress this week, with the arrival of the guys from Reilly Bric...
25/09/2026

Both the spec and Louie’s houses have made significant progress this week, with the arrival of the guys from Reilly Bricklayers to site Tuesday, to commence the limestone wall buildups!🙌🙌

Being that the sites are somewhat of a challenge with the slope on the blocks (thus the strip footing and buildup type of construction), and the limited access with the blocks only being about 10.5m wide, this job was always going to be a bit demanding!😬😬
But to all the guys credit, they accepted the challenge and have smashed it out, having a day left on Monday to finish the last section!👌👌

We needed to work in with the guys as they finished building the internal leaf of stone, because there also had to be a lot of steel work go into the cavity of the buildup walls prior to the guys building the outside leaf.

The reason for the steelwork and a larger cavity width than normal, and we will also fill the cavity with concrete later next week after the walls have dried out enough, essentially not only buildsup from the existing ground height, but also turns the walls into retaining walls, which means not having to change any landscaping to accommodate other garden retaining walls, like would be required if we did raft slabs!👍👍
More work now, but a gain in the long term!😃😃

Whilst we are still awaiting the arrival of Stephen and Sophie’s cladding, holding up progress somewhat, we are getting some other works and preparations happening!

Chris from MtG Excavations was on site to excavate the water and stormwater trenches, and dig down a pad for the rainwater tanks location, getting them low enough to create enough head of pressure to allow the water from the gutters to push through the stormwater pipe work to fill the tanks, and not overflow from the gutters!👍👌

Whilst doing all that trenching, he also added just one more trench for Michael, to be able to run the electrical cable and conduit to the shed for future power!👍👍

Inside, Taylor has got the priming and preparations for the waterproofing well underway, so by the end of next week, we will be ready to start laying tiles!😃😃

Leggo and Tarkyn continue their progress at Ben and Sushila’s house, getting all the brick walls to scaffold height this week, and starting the topping process. By the end of next week should see the guys very close to being done!🙏😃

Inside, Zayne and Jas got the ceilings hung early in the week allowing for Zayne to go ahead with the flushing process!😃😃
By Wednesday next week, the job will be completed with the sanding and cornicing all done, ready for the tilers to start the waterproofing process for this job also, then getting the cupboards installations happening too!👌👌

In between all that happening, we even managed to squeeze a couple of little concreting jobs in!🙄😂👌

Wayne at TNT decided to remove a little bit of landscaping and concrete it in, to enable the two shed forecourts to now be connected for a drive through!👍👍
While Lanya got a bit sick of having a slippery when wet, muddy track to her backyard so organised us to get a concrete path installed!👌👌

And fortunately/unfortunately for Nick, his hot water service died Thursday night, so we were able to replace the unit Friday!🙏🙌
Because, if it had’ve been Friday night before the AFL grand final, it may not possibly had the same outcome!🤷‍♂️🤷‍♂️😂😂

Ben and Sushila’s house is continuing its progress with Leggo still getting the bricks laid, even while he’s a man down ...
19/09/2026

Ben and Sushila’s house is continuing its progress with Leggo still getting the bricks laid, even while he’s a man down with Tarkyn away at trade school!👍👍

Inside, Zayne and Jas have been smashing out the insulation installation and hanging all the gyprock walls ready for the ceilings to go up, until Zayne got hit by the influenza A freight train, pretty stopping them in their tracks for the week!😬😬

After getting the speccy and Louie’s footings down last week, we had Chris and Lambert from MtG Excavations on site cleaning up and levelling the pad areas off, then getting some loads of filling sand, courtesy of Mick at Gambier Civil, inside prior to the buildup beginning, and ready for Bruhn Stone to deliver the pallets of stone to site!😁😁
Getting a full truckload of stone to site was a bit of a challenge, as unloading pallets of stone on an undulating road is never ideal for the buggy at the best of times, but you also don’t realise how busy a road North Tce is during the day, let alone come school pick up time!?😳😂
But the necessity of getting the stone in now overrides everything, as once the buildup begins next week, access to the back of the houses becomes very limited, so getting the stone in now was essential to keep the brickies happy in not having to cart the stone to far!🙌🙌

Steeline had Todd and Tieran’s roof delivered to site Thursday morning, ready for us to start sheeting after smoko, and smash out the back of the house sheets while the wind was calm for the day! We got a bit more done Friday, but between other jobs happening, we will now finish it off next week!🙏🙌

Taylor, Will and Matt have finished the floor tiling at JC and Niyo’s house, and got a start on the wall tilling too.👌👌
With the guys from CKK heading to site Monday morning to start fitting vanities and cupboards, the inside won’t be far off having the painters come in to get cracking, after the second fix carpentry is done!😃😃

There is always a sense of achievement and probably relief when you get the footings down on a job, but in the case of t...
12/09/2026

There is always a sense of achievement and probably relief when you get the footings down on a job, but in the case of the speccy and Louie’s houses, satisfaction as well for Ty, Tom and Elliot, being how much work it was to get to this point!🙌🙌
Next in line is to tidy up the site with the excavator ready for the stone to be delivered, ahead of the bricklayers starting the buildup!👍👍

Safwat and Salvana’s windows arrived on site thanks to the guys from Dowell Windows, ready for Crackers, Langa’s and Tex to install the following day. Now to keep cracking on with all the first fixings required, so we can get ready for gypocking and bricking up in the weeks to come!😁😁

After spending the previous week doing all the priming and waterproofing required at JC and Niyo’s, our three tilers in Taylor, Will and Matt got stuck into laying all the floor tiles this week!🙌🙌
Bit more floor tiling to finish and grouting to be done, and we will start on cupboards and wall tiling!👌👌

Crackers, Langa’s and Tex spent most of the week at Todd and Tieran’s house finishing fixing and bracing the last of the frames before erecting the trusses and installing facias!👌👍
With purlins next on the agenda, it won’t be long before we will be putting a lid on it!😃😃

This week we were back at Motel Mount Gambier finishing the third and final section of replacing all the old existing galv pipes for the cold water service!😃😃

We thought it best to get in before the busy holiday season really kicks in, now the weather is starting to turn for the better!

Ty, Tom and Elliot not only had to spend a day digging a trench for the new poly water line and the following days laying the new cold water mains and connections, but also contend with a neighbours staffy dog wanting to come through the fence to seemingly help them!😬🙄

Interestingly, the owner of the dog apparently thought it was a bit rude of the guys to be disturbing his staffy whilst they were working for a living and being contributors to society, when he tried his best to social interact!🤦‍♂️🤦‍♂️

I’m still trying to quantify old mates comment that if the dog gets through the barely standing, propped up fence and attacks them, that’s their fault!🤷‍♂️🤦‍♂️

But I guess, as he seems to be home all day belting out his favourite tunes, that he must be extremely busy keeping his house immaculately clean inside, cos mowing/slashing the grass in his backyard seems to have gotten on top of him, let alone putting any of his excess energy and possible skills to use, replacing the 19th century fence!🙄🙄🤦‍♂️🤦‍♂️
Stupid should hurt👊👊🤬🤬

Address

Riddoch Highway
Mount Gambier, SA
5290

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm
Friday 9am - 5pm

Telephone

+61408656699

Alerts

Be the first to know and let us send you an email when Mick Mullan Building and Plumbing posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share

Nearby engineering companies