31/03/2025
After months of hard work, we’re excited to have successfully completed the Mechanical Electrical works for the new stage at Bli Bli Good Samaritan School.
Collaborating closely with the primary mechanical contractors, we delivered:
- VRF wiring with interlinked outdoor air fans
- Toilet exhaust systems with VSD control & time clocks
- Fire mode shutdown for safety
- Mechanical switchboards with full function control
While the full BMS system was initially part of the scope, it was later removed from the project. We’re proud of the teamwork and dedication that brought this project over the finish line.”