We have a bird's eye view of progress at our Davyhurst village expansion which is expected to be operational by the end of June! This includes 100 additional rooms, plus a new 550-person dry mess and upgraded kitchen facilities.
We are also pleased to announce that Phase 2 has been approved ahead of the FY27 budget, which means construction of a further 124 rooms, along with recreation areas and a new gym which is planned to start in October. This phase will commence following the completion of our totally new camp at Siberia to accommodate our Sand King workforce!
We are investing heavily in our camps and facilities to support our growth strategy and it's great to see all the progress so far!