๐ง๐ฎ๐ป๐ฎ๐บ๐ถ ๐ฃ๐ฟ๐ผ๐ท๐ฒ๐ฐ๐ ๐ ๐ถ๐น๐ฒ๐๐๐ผ๐ป๐ฒ
A significant milestone for the Tanami site: a 138,000 kg Wรคrtsilรค engine has been safely transported, offloaded and positioned inside the Zenith Energyโs DBS Power Station. Once operational, the engine will contribute to reliable power generation to support operations at Tanami.
The engine was transported more than 3,700 km from Fremantle to the Tanami site over 10 days. The route across Western Australia, South Australia and the Northern Territory included a final 80 km section on challenging unsealed roads.
This achievement reflects outstanding planning, teamwork and collaboration between Newmont Australia, Zenith Energy and logistics contractors Milton Alternative Lifting/Tutt Bryant Group Limited.
Congratulations to everyone involved in delivering this milestone safely and successfully.
Wรคrtsilรค Energy Newmont Corporation