WEEK 13:1/2/3: Kitchen is installed (pt 1) ☑️4: Final Gyprock patch ☑️5: Vanities are installed ☑️6: Media room cabinet ...
12/07/2021

WEEK 13:
1/2/3: Kitchen is installed (pt 1) ☑️

4: Final Gyprock patch ☑️

5: Vanities are installed ☑️

6: Media room cabinet is installed ☑️

WEEK 12:Tile grouting finished ☑️ Front door installed ☑️Finish carpentry started; skirting, architrave and internal doo...
29/06/2021

WEEK 12:
Tile grouting finished ☑️

Front door installed ☑️

Finish carpentry started; skirting, architrave and internal doors ☑️

External paint completed ☑️

WEEK 11:Sand cement base complete ☑️Tiling done for the entire house ☑️Huge 600x1200m tiles ‼️
22/06/2021

WEEK 11:
Sand cement base complete ☑️

Tiling done for the entire house ☑️

Huge 600x1200m tiles ‼️

WEEK 10:First coat primer on walls and ceiling ☑️Water proofing in all wet areas installed ☑️Water proofing approved by ...
07/06/2021

WEEK 10:
First coat primer on walls and ceiling ☑️

Water proofing in all wet areas installed ☑️

Water proofing approved by Blacktown Council ☑️

WEEK 9:Wall and ceiling insulation complete ☑️Gyprock and wet area fibre cement board installed ☑️Plus all plastering an...
31/05/2021

WEEK 9:
Wall and ceiling insulation complete ☑️

Gyprock and wet area fibre cement board installed ☑️

Plus all plastering and sanding complete ☑️

Window glazing installed ☑️

WEEK 8:Cladding competed above lower roof ☑️Eves prepainted and installed ☑️Scaffolding down ☑️
24/05/2021

WEEK 8:

Cladding competed above lower roof ☑️

Eves prepainted and installed ☑️

Scaffolding down ☑️

WEEK 7:Electrical rough in completed ☑️ Blacktown Council frame inspection approved ☑️Extra blocking for wall hung vanit...
17/05/2021

WEEK 7:

Electrical rough in completed ☑️

Blacktown Council frame inspection approved ☑️

Extra blocking for wall hung vanities, TV and coat rails etc added ☑️

WEEK 6:Air con installed ☑️Lower roof and box gutter installed ☑️Hebel above lower roof installed ☑️Garage door blocking...
10/05/2021

WEEK 6:

Air con installed ☑️

Lower roof and box gutter installed ☑️

Hebel above lower roof installed ☑️

Garage door blocking completed ☑️

WEEK 5:Hebel installation ☑️Base render complete. And acrylic render complete ☑️Plumbing rough in completed ☑️
03/05/2021

WEEK 5:
Hebel installation ☑️

Base render complete. And acrylic render complete ☑️

Plumbing rough in completed ☑️

WEEK 4:Frame install completed ☑️Scaffolding up ☑️Fascia and gutter installed ☑️Scaffolding up and Fascia and Gutter ins...
26/04/2021

WEEK 4:
Frame install completed ☑️

Scaffolding up ☑️

Fascia and gutter installed ☑️

Scaffolding up and Fascia and Gutter installed ☑️

Roof Installed ☑️

WEEK 3:Full steel frame and windows delivered onsite ☑️
19/04/2021

WEEK 3:
Full steel frame and windows delivered onsite ☑️

WEEK 2:Termite collars are installed. Full formwork complete. Engineer and Council checks approved....ready for concrete...
13/04/2021

WEEK 2:
Termite collars are installed. Full formwork complete. Engineer and Council checks approved....ready for concrete to be poured ☑️

Concrete is poured ☑️

Concrete slab sealed to prevent cracks ☑️

External Drainage completed and connected to services. Surveyor marks slab and termite slab perimeter completed ☑️