23/03/2025
Burdell Benchmark :
Wow, what a statement these home owners have made.
We have just had some of the biggest rain fall events in Townsville over the last couple of months, and yet this property presents like this…..
No soft ground conditions, no water pooling, mowing straight after rain.
Quality and perfection would summarise the home owners dedication and desire for results achieved.
Photo timeline of project and basic phase completion as follows :
7/11/2024 : First day of the project, start undercutting and sub soil profile excavation.
9/11/2024 : Repair squashed 90mm stormwater pipes from when house phase was being built, and we found damage during the - 200mm undercut excavation.
12/11/2024 : Start garden bed structures around property.
14/11/2024 : Start Irrigation system installation layout.
16/11/2024 : Spread crusher dust over turf zones, and first load of McCahills topsoil arrives on site. Bulk spread of top soil started in turf zones.
21/11/2024 : Full site turf and irrigation completed. Ready for turf.
22/11/2024 : Rain starts 😕.
27/11/2024 : Top Notch Turf supply and installs Tahoma T31.
1/12/2024 : Irrigation times reduced as T31 has settled very well, plant layout begins.
14/12/2024 : Cylinder mower used and first lawn patterns cut in. ❤️.
Then the rains begin and massive amounts of water start to fall from above during the week around the 17/12/2024.
Xmas and new year periods, and home owners continue with additional planting.
More rain…..😕.
12/1/2025 : Planting layout completed by home owners.
Lots of rain, record falls over three week period in February, yet home and grounds in immaculate presentation. Rain fall measure in metres. 🌧️ ☔️.
8/3/2025 : Turf renovation begins as we move on from rain events as part of Autumn turf programme.
11/3/2025 : Finally the garden irrigation shrubblers installed and set. ( Mother Nature had been irrigating until now ).
12/3/2025 : Home owners carry out mulching of garden beds and apply products to turf zones.
17/3/2025 : Tahoma T31 has recovered post scalping and reset as part of lawn renovations.
21/3/2025 : Another rain fall event over 380 millimetres fell during this week alone. 🌧️☔️.
First mow since renovation and mow line showing stripes already.
23/3/2025 : Last three photos showing the amazing transformation and time line of this project. ❤️.
These property owners can stand tall and proud with the beautiful home they have built and created.
I’m very humble and proud to have been able to support them on the journey that has been the “ Burdell Benchmark”.
Project materials summary :
-) Approximately 40 Ton of site waste soil removed.
-) Minus 200mm sub soil profile was shaped and excavated.
-) Squashed stormwater pipes from build repaired.
-) 31 x Hunter rotor sprinklers, 42 x shrubblers sprinklers, and >200m of irrigation lines.
-) Garden beds materials : 76 x Linear metres of 200 x 50 H4 sleepers in 4.8m lengths.
-) 25mm Base of crusher dust used between subsoil and top soil layers.
-) 63Cm3 ( 88 Ton ) of topsoil used to obtain a 150mm soil profile.
-) Tahoma T31 turf with 25mm thickness profile to complete the 200mm foundations.