New Project | Masons Parade, Point Frederick Client: Owners Corporation Budget: $290kContract: Lump SumProject Duration:...
14/10/2026

New Project | Masons Parade, Point Frederick

Client: Owners Corporation
Budget: $290k
Contract: Lump Sum
Project Duration: 7weeks
Type of Project: Replacement of Garage Slabs & Retaining Walls
Scope of Works:
》Remove existing structures and dispose
》Remove existing failed brick retaining walls and concrete slabs
》Form and pour new engineered concrete slab to suit engineer’s design requirements
》Construct new concrete block retaining walls
》Core-fill new concrete block retaining walls

New Project | Crown Plaza, Terrigal Client: Buildcorp Budget: $45kContract: Lump SumProject Duration: 1  weekType of Pro...
14/10/2026

New Project | Crown Plaza, Terrigal

Client: Buildcorp
Budget: $45k
Contract: Lump Sum
Project Duration: 1 week
Type of Project: Remediation Works to Flag Pole
Scope of Works:
》Remove existing Flag Pole frame
》Remove existing brickwork down to the corroded tie downs and reinstate to match existing
》Concrete Spalling works throughout concrete parapet upstands
》Installation of remedial wall ties to support unstable brick infill panel

New Project | Smail St, Ultimo Client: Trescon Budget: $425kContract: Lump SumProject Duration: 8 weeksType of Project: ...
17/09/2026

New Project | Smail St, Ultimo

Client: Trescon
Budget: $425k
Contract: Lump Sum
Project Duration: 8 weeks
Type of Project: Heritage Remediation Works
Scope of Works:
》Repoint 20% of brickwork to all elevations
》Repair all failed brick arches with helical ties
》Repair large vertical structural crack and install crack stitching rods to help secure the repair
》Treat all facades with herbicide and pressure wash
》Remove existing brick infill panels to reveal previously closed up window penetrations to allow for new timber windows
》Remove existing brickwork and create new openings for 6 new timber windows

Project Update  | Albion Street, Surry Hills 》Our mission on this project was to make the facade watertight and protect ...
13/09/2026

Project Update | Albion Street, Surry Hills

》Our mission on this project was to make the facade watertight and protect the building for decades to come.

While we were in the process of carrying out these works, we identified a point of failure.

After a heavy week of recent rain, we were called to observe water making its way into the rafters of the Church.

In consultation with the client and Respected Roofing Services we designed a simple, effective way to replace the failed parapet box gutters with new copper trays and lead overflashing.

New Project | Albion St, Surry Hills Client: Squillace Architects Budget: $290kContract: Lump SumProject Duration: 8 wee...
30/05/2026

New Project | Albion St, Surry Hills

Client: Squillace Architects
Budget: $290k
Contract: Lump Sum
Project Duration: 8 weeks
Type of Project: Heritage Remediation Works
Scope of Works:
》Repoint two elevations to the aging church
》Replace all double stacked arch bars
》Repair large structural crack and install crack stitching rods to help secure the repair
》Treat both facades with herbicide and apply clear penetrable sealer
》Remove failed render from window sills and replace with appropriate render material
》Remove existing stained glass window, repair offsite and reinstate once repaired

New Project | Crown Road, Queenscliff Client: Strata Plan Budget: $490kContract: Lump SumProject Duration: 12 weeksType ...
30/05/2026

New Project | Crown Road, Queenscliff

Client: Strata Plan
Budget: $490k
Contract: Lump Sum
Project Duration: 12 weeks
Type of Project: Window Replacement and Cavity Flashing Installation
Scope of Works:
》Rectification Works - Involving the repair or replacement of defective window drainage, seals, glazing, flashings, and internal wall lining reinstatement.

New Project | Burns Place Park, Gosford Client: Central Coast Council Budget: $255kContract: Lump SumProject Duration: 9...
07/05/2026

New Project | Burns Place Park, Gosford

Client: Central Coast Council
Budget: $255k
Contract: Lump Sum
Project Duration: 9 weeks
Type of Project: Heritage Remediation Works
Scope of Works:
》Remove existing stone wall and arch ways
》Replace existing failed
》Reinstate stone wall and arch ways

New Project | The Entrance Board Walk Client: Private Budget: $415kContract: Lump SumProject Duration: 12 weeksType of P...
01/05/2026

New Project | The Entrance Board Walk

Client: Private
Budget: $415k
Contract: Lump Sum
Project Duration: 12 weeks
Type of Project: Replacement of Existing Awning & Replacement of Existing Metal Roof
Scope of Works:
》Provide scaffold access to roof work area
》Remove failed concrete block parapet
》Installation of SS tie back points to new core filled return walls
》Replace existing timber awning with new steel manufactured awning
》Replace existing roof sheeting to building

Address

16 Reliance Drive
Tuggerah, NSW
2259

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Telephone

+611300698579

Alerts

Be the first to know and let us send you an email when DeltaCorp Remedial Pty Ltd posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to DeltaCorp Remedial Pty Ltd:

Shortcuts

Share