03/06/2026
We’ve successfully installed one of the new electrical switchrooms, a critical asset that will ultimately power and control key elements of our full-scale HPA First Facility in Gladstone.
This milestone marks a clear transition for the project. With electrical works now mobilised alongside civil, structural, mechanical and piping disciplines, the site is moving into the next phase where permanent systems can be completed and progressively energised.
Over the coming week, we will complete access and finishing works before handing the area over to support the next stage of activity.
A strong milestone for the team and the first of many similar installations as the project continues to take shape. 👏