Orr Developments Inc.

Orr Developments Inc. General Contractor & Construction Management
www.orrdevelopments.com

✨Luxury living starts here at Sawmill Flats in Arnprior.
03/29/2026

✨Luxury living starts here at Sawmill Flats in Arnprior.

Making great progress at our riverfront home build in Renfrew at Carriage Landing last week. Drywall is done and mud and...
03/29/2026

Making great progress at our riverfront home build in Renfrew at Carriage Landing last week.

Drywall is done and mud and tape are underway, priming should follow soon.

Stay tuned for the exterior and interior finishes of this beauty.

Another strong week in Arnprior pushing ahead on Phase 3 of  💪The crew battled through some tough weather and a two-week...
03/29/2026

Another strong week in Arnprior pushing ahead on Phase 3 of 💪

The crew battled through some tough weather and a two-week engineering delay around the elevator shaft—but stayed locked in. With persistence and solid coordination, we pushed through and kept things moving.

Big milestone late Friday: the formwork crew stood the 18-foot elevator shaft walls, ready for rebar first thing Monday 👊

Last week also saw rock anchors completed, significant progress on waterproofing, and backfilling both inside and outside the parkade. We’ve now started prep for the Riverside retaining wall and knocked out a 110m vertical wall pour on Thursday.

The team is working hard, staying motivated, and ready to roll into another big week.

💪 This week was a productivity powerhouse! Our team made significant progress, mobilizing the rock anchor contractor and...
03/14/2026

💪 This week was a productivity powerhouse! Our team made significant progress, mobilizing the rock anchor contractor and overcoming weather delays.

The formwork, rebar and excavation crews excelled, pouring concrete and stripping forms despite tough site conditions. We hit the water table at the elevator shaft, but thrasher pumps and steel-toe boots saved the day. With the mechanical pits in place, we're gearing up for another massive week, starting with rebar installation of the elevator raft slab, forming and pouring more parkade walls, completing the rock anchors, waterproofing the exterior and backfilling.

Let’s keep this great momentum rolling, time to get back to work!

03/05/2026

All systems are a go with construction of Sawmill Flats Phase 3 in Arnprior. The momentum is strong, the team is motivated, and production is moving ahead better than ever.

🙌 Progress update on this stunning riverfront home at Carriage Landing in Horton, Ontario.We’re moving along nicely and ...
03/03/2026

🙌 Progress update on this stunning riverfront home at Carriage Landing in Horton, Ontario.

We’re moving along nicely and right on track to have this one wrapped up by summer — just in time to enjoy boating season on the Ottawa River.

Progress update from site 👊This week we poured a 40-metre section of 4-metre-tall below-grade parking garage walls. With...
02/28/2026

Progress update from site 👊

This week we poured a 40-metre section of 4-metre-tall below-grade parking garage walls. With a lot of manpower and winter heat, we came back the next morning to a clean, mirror-like finish. The crew earned that one.

After 10 weeks of blasting and breaking rock, the demo phase is officially complete. Now we’re excavating further to open up more ground for our foundation and rebar teams.

Next up: drilling 13 rock anchors through the raft slabs, extending 8 metres down into bedrock to meet seismic requirements. These anchors essentially tie the building into the rock for the life of the structure — serious work that never gets seen once the project is finished.

As we continue pushing up foundation walls, we’ll move into waterproofing, backfilling, and preparing to bring services into the building.

The momentum is building here on Phase 3 at Sawmill Flats in Arnprior. The fun is just getting started.

We’ve been making great progress on Phase 3 at  Sawmill Flats in Arnprior! This week we mobilized our foundation and reb...
02/21/2026

We’ve been making great progress on Phase 3 at Sawmill Flats in Arnprior! This week we mobilized our foundation and rebar crews and wrapped up over 250 meters of concrete pours, including mud slabs, raft beam slabs, and strip footings.

Next up: tall parking garage walls. Looking forward to the next stage of this build and sharing more updates as we go!

Hyde Construction Limited

We’ve been a little quiet on social media lately, but behind the scenes there’s been plenty of progress happening at the...
02/06/2026

We’ve been a little quiet on social media lately, but behind the scenes there’s been plenty of progress happening at the Phase 3 Apartment Project.

This final phase will complete the community with a 5-storey, 58-unit apartment building featuring below-grade heated parking and storage. We’re proud to be part of this project and excited to continue building in the great town of Arnprior!

In partnership with we can’t wait to showcase this beautiful luxury riverfront apartment building overlooking the Madawaska River.

🏡 New Home Update:We’re rebuilding a new waterfront home at Carriage Landing outside of Renfrew that unfortunately suffe...
11/23/2025

🏡 New Home Update:

We’re rebuilding a new waterfront home at Carriage Landing outside of Renfrew that unfortunately suffered a fire. The new home will have a very similar layout and design — but we’re torn on the exterior!

Which look do you prefer: the original black exterior or a fresh white façade?

Comment below and let us know your pick! 👇

We wrapped up a full terrace restoration this week at the Arnprior Motor Inn. The 60-year-old pre-cast terrace was remov...
11/06/2025

We wrapped up a full terrace restoration this week at the Arnprior Motor Inn. The 60-year-old pre-cast terrace was removed, new structural steel and metal decking were installed, and we poured and finished a brand-new slab.

The owners were fantastic to work with — truly great people. If you’re ever looking for a place to stay in Arnprior, we highly recommend checking out their motel. The pride of ownership really shows. ✅

Address

580 White Lake Road
Arnprior, ON
K7S3G9

Alerts

Be the first to know and let us send you an email when Orr Developments Inc. posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share