Stirling Place update.  Windows in and Masonry started on the exterior.  Corridor and demising wall framing complete on ...
07/25/2025

Stirling Place update. Windows in and Masonry started on the exterior. Corridor and demising wall framing complete on all floors complete and ready for board and insulation. 90% complete plumbing in underground parking.

It’s been a minute since we’ve updated for Stirling Place, but progress continues due to our hard working trade partners...
06/18/2025

It’s been a minute since we’ve updated for Stirling Place, but progress continues due to our hard working trade partners. Exterior frame and board is nearly complete thanks to Roy Drywall., with hot on their tail with Blueskin.

is making quick work of roofing at the same time.

At this time, while investigations are still ongoing at our Stirling Place project following an unfortunate accident.  W...
05/31/2025

At this time, while investigations are still ongoing at our Stirling Place project following an unfortunate accident. We would just like to take this opportunity to extend our deepest sympathies to the injured worker and his family. Our hearts go out to them, as we wish for the best recovery and outcome that could be expected in light of this event.

We would also like to extend our deepest gratitude and sincere respect to the incredible first responders, emergency medical personnel, and all involved in the rescue efforts at our site earlier this week.

In an extremely challenging situation, their professionalism, collaboration, and unwavering focus led to the successful and safe extraction of the worker. Due to the complexity of the incident, it may appear as though it took too long to carry out the rescue, however the duration of the extraction highlights the careful, deliberate measures taken to ensure the safety of everyone involved.

This gratitude goes out to the following agencies:
• Brockville Fire Department
• Ottawa Fire Services
• Brockville Police Services
• Leeds and Grenville Paramedics
• Elizabethtown-Kitley Fire Department
• Ornge Air Ambulance
• The doctors and nurses at Brockville General Hospital
• All the contractors that took action and assisted first responders
• The doctors, nurses and support staff at the Kingston General Hospital

In the meantime, we are fully cooperating with the Ministry of Labour and Brockville Police Service as they carry out a thorough investigation. We remain committed to doing everything possible to assist in determining the cause of the incident and to ensuring that such a tragedy never happens again.

Stirling place topped off the penthouse at the start of last week. Thanks again  , you crushed it on this one.Framing un...
05/18/2025

Stirling place topped off the penthouse at the start of last week. Thanks again , you crushed it on this one.

Framing underway, time to get this thing closed in!

In less than a week, underground plumbing is complete and ready for backfill thanks to our plumbers and For working so well together.

3rd floor slab and columns poured.  On to the 4th floor!
04/16/2025

3rd floor slab and columns poured. On to the 4th floor!

 putting in the work to keep the job going on the weekend.  Thank you for the hard work to keep the project on schedule....
04/12/2025

putting in the work to keep the job going on the weekend. Thank you for the hard work to keep the project on schedule. Lots of respect for what these workers can pull off.

Another floor poured thanks to the hard work of  and concrete supply from
04/04/2025

Another floor poured thanks to the hard work of and concrete supply from

Columns are peaking over the fence line, 2nd floor sky deck well underway, foundation waterproofing and insulation insta...
03/26/2025

Columns are peaking over the fence line, 2nd floor sky deck well underway, foundation waterproofing and insulation installed, and backfill to keep a nice clean site.

Stirling Place ground floor slab poured and verticals going up!
03/19/2025

Stirling Place ground floor slab poured and verticals going up!

Tower crane is up, ground floor slab almost ready to pour.  There’s no slowing down now!
03/14/2025

Tower crane is up, ground floor slab almost ready to pour. There’s no slowing down now!

Some aerial shots of Stirling Place. Ground floor deck is ready for rebar!
03/13/2025

Some aerial shots of Stirling Place. Ground floor deck is ready for rebar!

Ground floor skydeck and slab edge is well on its way already, let’s go!  Thanks to our great Formworkers.
03/06/2025

Ground floor skydeck and slab edge is well on its way already, let’s go! Thanks to our great Formworkers.