2024-07-08
Over the past few weeks, our team has been preparing a plan and timeline and completing initial work for a feasibility study to determine if a business case exists to build a new mill in Liverpool, Nova Scotia, producing up to 600,000 air dry metric tonnes (ADMT/year) of Northern Bleached Softwood Kraft Pulp (NBSK).
This initial work included gathering third-party input for preliminary technical details such as capital expenditure estimates, wood, water, chemical consumptions, construction schedules, and production ramp-up information. We are also engaging independent consulting firms to support our team in validating the analysis and developing a summary report.
Over the next few weeks, we will issue a request for proposals (RFP) for consultants to confirm capital costs and begin studying wood supply and logistics.
Significant work and analysis must be completed between now and January 2025 to determine if a new mill is viable. To be considered feasible, the Internal Rate of Return (IRR) over 20 years must be at least 14%. To determine the IRR, we will assess the estimated cost of construction, delivered wood, start-up and operation, labour, and funding and financing structures, among many other items. We will also assess the price and market for the pulp and any other bioproducts the mill could produce.
If the IRR over 20 years is less than 14%, we will not proceed with a new mill and will begin divesting our assets through a managed CCAA process.
If the IRR over 20 years is at least 14%, we will begin the estimated 4-year process for detailed design, financing, regulator approvals and permits, and building and commissioning a new, modern mill.
We will provide updates on our progress throughout the nine-month feasibility study.