Denison Mines Corp

Denison Mines Corp Uranium Development & Exploration in the Athabasca Basin, Canada. Highlighted by its Wheeler River development project & 350k hectares of exploration land.

Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan – including its 60% owned Wheeler River project, which hosts the high grade Phoenix and Gryphon uranium deposits.

Long-lasting relationships begin with listening.Last week, Denison was honoured to participate in the Métis Rights and E...
08/20/2026

Long-lasting relationships begin with listening.

Last week, Denison was honoured to participate in the Métis Rights and Engagement Gathering in Southbay, where we had the opportunity to learn and continue building relationships based on respect, understanding, and collaboration.

We extend our sincere thanks to Minister Merasty and Northern Region 3 of Métis Nation–Saskatchewan for welcoming us to this event.

Thank you to everyone who organized the gathering and to the Southbay community for your warm welcome.

Thank you to everyone who made Back to Batoche such a great event again this year. Denison was proud to support this ann...
08/17/2026

Thank you to everyone who made Back to Batoche such a great event again this year.

Denison was proud to support this annual celebration of Métis culture and sponsor the Vermette Raceway, where Indigenous equine talent was on full display.

We enjoyed being part of the festivities and celebrating alongside the many participants, volunteers and visitors who make this event possible.

Denison Reports Financial and Operational Results for Q2 2026, Highlighted by Significant Initial Progress from Construc...
08/13/2026

Denison Reports Financial and Operational Results for Q2 2026, Highlighted by Significant Initial Progress from Construction Activities at the Phoenix In-Situ Recovery ('ISR') Uranium Mine.

David Cates, President and CEO of Denison commented, "Since the commencement of on-site activity at Phoenix in March 2026, we have advanced critical site preparation activities, including completion of over 20% of the total project site civil work and nearly 100% of the civil subgrade work needed for the process plant and wellfield areas, plus the installation of construction management and temporary camp facilities.

Critical first-year construction milestones are on track, including pouring of the concrete foundations for the process plant and main power transformer, commencement of installation of the freeze wall, installation of on-site power distribution, and establishment of the airstrip.

This quarter's financial results highlight the successful ex*****on of our multi-year project financing strategy to monetize the 2.5 million pounds U3O8 of physical uranium acquired in 2021. These holdings were acquired at an average cost of $36.67 (US$29.66) per pound U3O8 and we have been judiciously selling into a market of strengthening uranium prices. In Q2, we sold 750,000 pounds U3O8 for an average realized price of $122.16 (US$89.17) per pound U3O8, which generated over $90 million in proceeds and a $64 million (233%) realized gain compared to the original purchase price. Importantly, these transactions provide meaningful funding for Phoenix without dilution to our shareholders.

Denison is now fully engaged in a critical and exciting phase of growth. With significant construction progress being made daily at Phoenix, the Company having an active presence in the global uranium marketplace, and our continued investment in future growth through exploration and project development, we are well positioned to offer shareholders unique exposure to the uranium market at a time of growing recognition that the sector's fundamentals are robust and likely to continue improving."

Read the full press release here: https://ow.ly/Wqr350ZzzNS

Denison Reports Financial and Operational Results for Q2 2026, Highlighted by Significant Initial Progress from Construc...
08/13/2026

Denison Reports Financial and Operational Results for Q2 2026, Highlighted by Significant Initial Progress from Construction Activities at the Phoenix In-Situ Recovery ('ISR') Uranium Mine.

Read the full press release here: https://ow.ly/ziuF50ZzoGy

Record participation and plenty of great catches made this year's Uranium City Fish Derby a success.The event brought co...
08/11/2026

Record participation and plenty of great catches made this year's Uranium City Fish Derby a success.

The event brought community members together for a day of fishing, friendly competition, and time spent on the water.

Denison was proud to support this long-standing community event. Congratulations to everyone who participated, and to this year's winners!

Denison Announces Completion of Site Preparation Activities and Commencement of Full-Scale Construction at Phoenix ISR U...
07/28/2026

Denison Announces Completion of Site Preparation Activities and Commencement of Full-Scale Construction at Phoenix ISR Uranium Mine.

David Cates, President & CEO of Denison, commented, "Completing the site-preparation activities needed to ramp up our on-site workforce and achieve a full-scale rate of construction is an important initial milestone for the Phoenix project.

Site civil work has progressed well during the early works program, with +20% of overall site civil work estimated to be completed to date. Importantly, we have achieved near 100% completion of civil subgrade work for the process plant and wellfield areas, which is needed to facilitate the planned concrete pour for the plant and the initiation of the freeze wall installation program.

Construction activity is expected to accelerate through the remainder of the summer months with the commencement of a second shift, which means seasonally sensitive civil and other construction work can continue virtually 24-hours a day in support of the completion of our key first-year construction milestones – including concrete pours of the foundations for the process plant and main power transformer, installation of the freeze wall, as well as earth works for the airstrip and on-site power distribution.

Achieving these positive early results demonstrates the readiness and commitment of Denison and our construction partners as we advance this unique nation-building project to become Canada's first new large-scale uranium mine since Cigar Lake."

Read the full press release here ⬇️
https://ow.ly/JeBn50ZtOpk

Denison Announces Completion of Site Preparation Activities and Commencement of Full-Scale Construction at Phoenix ISR U...
07/28/2026

Denison Announces Completion of Site Preparation Activities and Commencement of Full-Scale Construction at Phoenix ISR Uranium Mine.

Since the commencement of site preparation and early works in March 2026, significant progress has been made by Denison and its construction partners to complete several critical site preparation activities – including substantial completion of site clearing activities, advancement of schedule-sensitive site civil works, the establishment of construction management facilities, and the initiation of perimeter freeze wall installation for Phase 1 of the mine.

Read the full press release here: https://ow.ly/BVG650ZtOfp

We are hiring!  The Procurement Coordinator is responsible for supporting the procurement process from sourcing through ...
07/23/2026

We are hiring!

The Procurement Coordinator is responsible for supporting the procurement process from sourcing through delivery.

See if this role is right for you!

Click here to learn more about the position: https://ow.ly/qk8h50Zs3Ui

Our President & CEO, David Cates, joins Robert Quinn on Leading Through Uncertainty to discuss leadership, navigating ma...
07/20/2026

Our President & CEO, David Cates, joins Robert Quinn on Leading Through Uncertainty to discuss leadership, navigating market cycles, and Denison's decision to pursue in situ recovery (ISR) as an innovative approach to uranium mining in Canada.

Watch the full interview here: https://ow.ly/mWpS50Zq6te

Celebrating 250 years is a remarkable milestone, and we were honoured to join the community of Île-à-la-Crosse in markin...
07/16/2026

Celebrating 250 years is a remarkable milestone, and we were honoured to join the community of Île-à-la-Crosse in marking this historic occasion.

From boat tours and traditional leather mitt-making to medicine demonstrations, square dancing, music, yoga on the beach, fresh lii bang, and shared meals, the festivities offered opportunities to connect with the people, culture, and history that make Île-à-la-Crosse such a special place.

Congratulations to the community of Île-à-la-Crosse on this significant anniversary, and thank you for welcoming Denison to be part of the celebration.

Address

1100/40 University Avenue
Toronto, ON
M5J1T1

Alerts

Be the first to know and let us send you an email when Denison Mines Corp posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Denison Mines Corp:

Shortcuts

Share

Category