Dean Construction

Dean Construction Marine Construction / Dredging / Deep Foundations

Dean Construction will have a two-crew commercial diving division in place and functional this Spring.We're excited to b...
02/21/2026

Dean Construction will have a two-crew commercial diving division in place and functional this Spring.
We're excited to bring these new personnel, capabilities and efficiencies in-house.
In the long-term, these investments and new faces will make Dean even more competitive.

Waterfront Toronto and Eastern Construction have forwarded a project outline and a time-lapse video of Dean's efforts at...
12/23/2025

Waterfront Toronto and Eastern Construction have forwarded a project outline and a time-lapse video of Dean's efforts at the Parliament Street Slip in Toronto.

Timelapse video link:
https://www.youtube.com/watch?v=S-kuRaOxX4A

Waterfront Toronto's project description:
https://www.waterfrontoronto.ca/news/parliament-slip-preparing-future-mobility-network

Dean is currently starting the next phase of the project, hopefully with many more phases to construct in the future as Toronto redefines its waterfront.

Home News Parliament Slip: Preparing For The Future Mobility Network Parliament Slip: Preparing for the Future Mobility Network Image PUBLISHED: December 19, 2025 In This Blog:Learn why a portion of Parliament Slip was lakefilled and how it supports the future mobility network across the...

Dean Construction completed the 2025 works for the water intake structure at Ontario Power Generation's Darlington New N...
12/06/2025

Dean Construction completed the 2025 works for the water intake structure at Ontario Power Generation's Darlington New Nuclear Plant in October. Completion of this work on schedule and budget required the 24/7 dedication of Dean's crews

The 2025 works included the dredging of the intake footprint, the drilling of the shaft for the intake riser, as well as the supply and placement of the steel intake liner and its sealing to the bedrock.

Dredging of the hard (blow counts in excess of 100 BPF) glacial till at the intake footprint required the use of a vibrating ripper tooth and the subsequent excavation using rock buckets and a hydraulic clamshell bucket. All of the pre-treatment and excavation was performed with Dean's 190t hydraulic excavator from a spud barge. Approximately 5m of till was removed and the bottom of the excavation was in water depths exceeding 19m.

The shaft for the intake liner was drilled using an array of holes created with a down-the-hole cluster bit. The finished inner diameter of the shaft was 8m and required the removal of approximately 16m of bedrock.

The 6m inner diameter steel intake liner and its cap were fabricated in Hamilton and delivered by barge to the site. It was inserted in the shaft and it's anulus sealed with concrete.

Dean's 2026 works on the site will involve pressure-testing the liner, constructing the base for the intake structure, installing the precast concrete intake modules, removing the liner's cap and placing the final section of the intake.

All of us at Dean would like to thank Aecon and Ontario Power Generation for the opportunity to work on such a unique, legacy project.

Dean Construction completed the installation of twenty-two outfall risers for Ontario Power Generation's Darlington New ...
12/06/2025

Dean Construction completed the installation of twenty-two outfall risers for Ontario Power Generation's Darlington New Nuclear Project in September of 2025. These outfall structures will discharge warm water from the new power plant at a depth and location which protects the environment.

The 1.036m diameter, stainless steel risers were approximately 19m long and installed in Lake Ontario, with water depths averaging 12m.

Sacrificial steel liners were installed through the glacial till and seated on the bedrock. Rock drilling was accomplished in a single pass using a down-the-hole cluster bit. The liners were fabricated off-site and then barged to the site and inserted in their respective holes. Their annuli were then grouted to seal the liner-bedrock interface. Protective rock scour protection was then placed on the lake bed around each riser.

In the future, the tunnel boring machine will pass by each of the risers' bottoms and workers will mine from the tunnel to the risers connecting them. When tunneling operations are complete Dean will return to the site, open valves on the risers and flood the tunnel. When flooding is complete, caps at the tops of the risers will be removed and the outfalls will be functional.

Dean Construction is very proud to be involved in this nation-building enterprise and look forward to more such works.

We're currently dredging Wharf 10 for the St. Lawrence Seaway Authority.  There's a 13 km transit through the Welland Ca...
10/18/2025

We're currently dredging Wharf 10 for the St. Lawrence Seaway Authority. There's a 13 km transit through the Welland Canal between the dredge site and the offloading dock, then the material is being trucked and deposited in an on-shore containment facility.
It's always great to work for the Seaway Authority.

The Darlington New Nuclear Project (where Dean is the dedicated marine subcontractor) is listed as one of Prime Minister...
09/11/2025

The Darlington New Nuclear Project (where Dean is the dedicated marine subcontractor) is listed as one of Prime Minister Carney's five Nation-Building works.

Prime Minister Mark Carney unveiled several “nation-building” projects Thursday morning that his government identified as part of a promise to bolster Canada's economic independence amid a turbulent trade war.

New Year, new gear.This is our Hitachi EX-1900 (210-tons, truck for scale) and its attachments, ready to go to our Darli...
01/21/2025

New Year, new gear.
This is our Hitachi EX-1900 (210-tons, truck for scale) and its attachments, ready to go to our Darlington job.

Address

2720 Front Road
Windsor, ON
N9J2N5

Opening Hours

Monday 7am - 5pm
Tuesday 7am - 5pm
Wednesday 7am - 5pm
Thursday 7am - 5pm
Friday 7am - 5pm
Saturday 7am - 12pm

Telephone

+15197348999

Alerts

Be the first to know and let us send you an email when Dean Construction posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Dean Construction:

Share