08/01/2026
2025 has been a standout year for EW — delivering major impact across every division.
🔌 Fibre Division
• Over 21,000 fibre installs completed across NI & Cumbria
⚡ Power Division
⚡Distribution Network
• 210km of 11kV Overhead Line Rebuild
• Over 28000 LV poles surveyed
• Over 30000 HV poles surveyed
• Over 30000 properties surveyed
⚡Transmission Network
• Various Transmission schemes completed including 110KV pole replacements – 86 pole sets replaced, 100 tower step-bolts replaced, colour plates and number plates, 275KV tension and suspension insulator replacements ,110KV tower inspections – 103 towers inspected.
110KV – 19.9KM of old earth-wire recovered and new strung. This included crossing over a railway line, motorway, 1 x 275KV overcrossing, 1 x 33KV crossing, 23 x 11KV crossings and 7 x LV crossings &12 fibre splices also completed.
110KV AP1 pole replacements – 24 x AP1 poles replaced, repositioned and new poles erected.
🌬️ Major Projects Division
• 15 km of 33kV ICP/IPP windfarm grid connections delivered
We are extremely proud of our teams who made this possible — and excited for 2026,