29/08/2026
π§ WORKSHOP UPDATE | REFRIGERATION PIPEWORK PREFABRICATION
Progress continues in the OWS Engineering workshop on a new refrigeration pipework installation for Thistle Seafoods, Scotland.
While we await delivery of the buffer tank and duty/standby pump set, our fabrication team is getting ahead of the programme by carrying out a mock set-up and fabrication of the associated pipework spools.
By establishing the equipment positions and pre-fabricating as much of the system as possible within our workshop, we can progress the pipework towards completion before the remaining equipment arrives.
This approach helps us to:
βοΈ Maximise off-site fabrication
π Verify spool arrangements and fit-up
β±οΈ Reduce installation time on site
π§ Minimise modifications during installation
π
Maintain programme efficiency and support early project delivery
A good example of how planning ahead at the fabrication stage can make a significant difference at installation.