Itโs been a busy, HOT summer so far! ๐๐ป๐๐ฅต
We have been working on numerous projects lately so we havenโt posted much at all but hereโs an update on the one barn job we are currently working on.
โ
steel portal frame barn dismantled
โ
concrete slab and walls crushed on site
โ
footings pulled out over 6 pours due to ground make up, depth and access
โ
footings poured
โ
new steel posts installed to mimic existing barn layout
โ
bricked up to dpc ready for services and block and beam floor to be installed
This is a cracking job all round, at the moment we have โslightโ issues with planners due to bi-fold door locations and class Q planning but it is being ironed out currently so hopefully a compromise can be made swiftly ๐ค๐ปand we can start getting this build up to wall-plate asap ๐๐ป