First time for everything. Building over a canal.
This job had 18 months of admin and preparation. Probably as much time on paperwork as there was building the actual wall.
All said and done it went well. The Canal & River trust commented that we went above and beyond the code of conduct.
Our client was also happy the job was completed 5 days earlier than the site schedule.
Well done all & thanks to my scaffolders too, without them the job would not have happened.