24/03/2022

We initially thought this part of the project would take four weeks, however, for various reasons, it has turned into eleven! Some advised me to walk away…so to be now at the point to be pouring concrete for the first time is an amazing feeling! Sometimes success is just on the other side of failure 😄

05/02/2022

Committed to meeting the programme deadline, our team is working throughout this weekend to push the ground works section of this project on…which has entailed removing nearly 250 cubic tonnes of concrete! We will soon begin pouring a new concrete slab, installation of new service pipework, insulation and wet underfloor heating throughout!

It may be a cold start to the week….but we’re making great progress at this double storey extension!! Hope you’ve all ha...
29/11/2021

It may be a cold start to the week….but we’re making great progress at this double storey extension!! Hope you’ve all had a lovely weekend 😊

19/10/2021

Having to crane the new windows into position was a challenge to say the least, but wow, they look amazing! Can’t wait to show the finished projects!!

13/10/2021

New project started!! Stepping this one up a little, with a double-storey extension, plus converting the loft and garage!

24/09/2021

Half way through our first structural project and we are on schedule and our clients are happy, which is always our main priority!!