30/10/2026
🪨 PHASE 3 - EASTERN QUARRY 🪨
All Access were recently appointed to take over the scaffolding works at Phase 3, Eastern Quarry in Ebbsfleet, after the previous scaffolding company unfortunately went into administration.
In just 4 weeks, our operatives have impressively based out 2 apartment blocks and 43 houses, many of which have also been raised up to 2nd, 3rd and 4th lifts.
With the programme being negatively impacted with each passing day, this meant that the quotation and mobilisation period was incredibly short.
With this in mind, our team all pulled together to get this over the line and got us on site as soon as possible to give the client the best chance of recuperating their programme.