27/10/2025
Milestone Monday – Week 12 | Shenley Wood, Site B, Milton Keynes
Our team is making fantastic progress on site this week and preparing for the next phase of delivery!
🏗️ Foundations – 80% complete on Unit 2
🌍 Earthworks – 90% complete across the site for Units 1 and 2
🔩 Steel frame – due to start week commencing 3rd November
This exciting project sees the design and construction of two sustainable industrial warehouse units in Milton Keynes, providing a total of 144,222 sqft of high-quality space within a 39-week build programme.
We are proud to be working collaboratively with our client, Hampton Brook, and the professional team bring this development to life.