04/08/2026
"We can't afford to go solar right now."
It's the most common reason businesses delay — and it's often based on an outdated
assumption: that on-site solar means a big capital outlay and a maintenance headache.
Here's how the deal at Marelli's Sunderland plant actually works:
✅ A 2.4MW solar and battery system, funded in full — zero upfront cost ✅ Marelli simply buys
the solar power it generates at 10.6p/kWh — less than half the current market rate ✅ The
system is fully maintained for the entire 25 years, including inverter replacements every 12
years ✅ At the end of the term, Marelli owns the system outright — at no cost
No cheque to write. No maintenance to manage. And a valuable asset owned free and clear at
the end — on top of £100,000+ in projected year-one savings and 345 tonnes of CO₂ prevented.
Fusion Power Solutions originated the project, introducing Marelli to Arin Power for the design,
with SNRG funding it.
The takeaway: cutting your energy costs and your carbon doesn't have to start with a cheque. It
starts with the right conversation.
If "we can't afford it" has been holding your site back, it's worth a second look.
https://www.linkedin.com/pulse/snrg-overcomes-grid-restrictions-power-marelli-factory-our-snrg-ieose?utm_source=share&utm_medium=guest_desktop&utm_campaign=copy