The site has moved on. Has your programme?Under NEC4 ECC, the Accepted Programme is a working commercial tool. Keeping i...
28/10/2026

The site has moved on. Has your programme?

Under NEC4 ECC, the Accepted Programme is a working commercial tool. Keeping it current helps the team understand progress, remaining work and the effects of change.

For groundworks and civils teams, a useful update should:

• Record actual progress and its effect on the remaining work.
• Show realistic sequencing, access requirements and interfaces with others.
• Explain how delays and notified Defects will be dealt with.
• Reflect time impacts even where compensation event status is unresolved—make that status clear.

Submit revisions for acceptance at intervals no longer than those stated in the Contract Data, and track the response. Keep a clear record of which revision is accepted.

A programme showing a delay does not, by itself, establish compensation event entitlement. Programme acceptance and the compensation event process need separate attention.

Check your NEC4 ECC requirements, Scope and amendments, including Z clauses.

Moore QS provides practical commercial support for contractors. Yorkshire-based, working nationwide.

Need a second pair of eyes on your programme and commercial records? Drop me a message.

The lowest quote can still leave you with the biggest gap.Before placing a groundworks or civils package, check that eac...
26/10/2026

The lowest quote can still leave you with the biggest gap.

Before placing a groundworks or civils package, check that each subcontractor has priced the same job.

A useful comparison goes beyond the total:

• Are the drawings, revisions and quantities consistent?
• Who provides plant, temporary works, testing and waste disposal?
• Are mobilisation, return visits and phased working included?
• What access, programme and working-hour assumptions underpin the price?
• Which exclusions leave a cost for your own team to carry?

Put a realistic allowance against the gaps before comparing the offers.

Then resolve the clarifications and capture the agreed scope in the order. A conversation during tendering is easy to lose once the work starts.

Moore QS supports contractors with procurement and practical commercial management. Yorkshire-based, working nationwide.

Got a package where the quotes are difficult to compare? Drop me a message.

Don’t let the notification deadline pass while you’re pricing the event.Under standard NEC4 ECC clause 61.3, the contrac...
21/10/2026

Don’t let the notification deadline pass while you’re pricing the event.

Under standard NEC4 ECC clause 61.3, the contractor generally has eight weeks from becoming aware that an event has happened to notify it as a compensation event. Recognising its contractual significance later does not restart that clock.

Missing the deadline can prevent changes to the Prices, Completion Date or Key Dates.

There is an exception for events arising from specified instructions, notifications, certificates or changed decisions by the Project Manager or Supervisor. Check the actual contract, including Z clauses, before relying on the standard period or exception.

A practical routine for your site and commercial teams:

• Log what happened and when you became aware.
• Explain why you believe it qualifies as a compensation event.
• Send a separate notification to the Project Manager using the contractual communication route.
• Keep dated photographs, instructions, site diaries and labour, plant and material records linked to the event.
• Track the response and the next action.

Notification and quotation are separate stages. Don’t delay the notification while waiting for every invoice or the final cost.

Moore QS provides practical commercial support for contractors. Yorkshire-based, working nationwide.

Want a second pair of eyes on your compensation event process? Drop me a message.

Delivered to site doesn’t mean installed in the job.On groundworks packages, the gap between materials bought and work c...
19/10/2026

Delivered to site doesn’t mean installed in the job.

On groundworks packages, the gap between materials bought and work completed can quietly reduce the margin.

Pick a major material and check:

• What quantity was allowed for the work completed?
• What has actually been delivered?
• What usable stock remains on site?
• Have returns, transfers and credits been recorded?

Compare quantities on the same basis. Tonnes delivered and compacted cubic metres installed need a sensible conversion before the numbers tell you anything useful.

Investigate the difference. It could be waste, over-ordering, a changed specification or extra work that needs recording.

Catch it while you can still adjust the next order.

Moore QS provides practical commercial support for contractors. Yorkshire-based, working nationwide.

Want a clearer view of where your material budget is going? Drop me a message.

“We sent an early warning” isn’t the same as “we notified a compensation event”.Under NEC4 ECC, these processes serve di...
14/10/2026

“We sent an early warning” isn’t the same as “we notified a compensation event”.

Under NEC4 ECC, these processes serve different purposes.

An early warning flags a matter that could affect cost, Completion, a Key Date or the performance of the works. It gives the team an opportunity to reduce the risk.

A compensation event notification deals with an event that has happened—or is expected to happen—and is believed to qualify under the contract.

For groundworks and civils teams, the practical check is simple:

• Raise risks promptly through the correct contractual channel.
• Review separately whether a compensation event notification is required.
• Where both notifications are required, issue them separately.
• Record the actions agreed and follow them through.

Don’t assume an entry in the Early Warning Register has completed the compensation event notification process.

Check your contract and amendments, including the applicable notification requirements.

Moore QS provides practical commercial support for contractors. Yorkshire-based, working nationwide.

Need a second pair of eyes on your NEC processes? Drop me a message.

The gang stayed busy. Did the job move forward as priced?A labour allowance depends on the output behind it. If a draina...
12/10/2026

The gang stayed busy. Did the job move forward as priced?

A labour allowance depends on the output behind it. If a drainage run takes longer than allowed, the extra gang and plant time can reduce the margin—even when the work is within scope.

A useful weekly check:

• What quantity was completed?
• How much labour and plant time did it take?
• How does that compare with the tender allowance?
• What affected progress: access, ground conditions, deliveries or rework?

Record the reason while the detail is fresh. Separate changes in scope from productivity losses so you can decide what needs pricing, investigating or correcting.

Use actual progress to update the allowance for the remaining work.

Moore QS provides practical commercial support for contractors. Yorkshire-based, working nationwide.

Want a clearer view of where a package is losing time and margin? Drop me a message.

Applied for. Agreed. Paid. Three different numbers.A submitted valuation shows what you’ve asked for. It doesn’t show wh...
07/10/2026

Applied for. Agreed. Paid. Three different numbers.

A submitted valuation shows what you’ve asked for. It doesn’t show what has been agreed or what has reached the bank.

For each live groundworks or civils package, keep a clear record of:

• The amount applied for
• The amount assessed or agreed
• Retention and other deductions
• The expected payment date
• The amount actually received

Where there’s a gap, record the reason, the next action and who is following it up.

Build your cash forecast around realistic receipts. Keep disputed or unconfirmed amounts visible so you can see how a delay would affect the weeks ahead.

Moore QS provides practical commercial support for contractors. Yorkshire-based, working nationwide.

Want a clearer view of what’s due and what needs chasing? Drop me a message.

The estimator priced a plan. Does the site team have it?A tender can allow for a particular gang, sequence and output. I...
05/10/2026

The estimator priced a plan. Does the site team have it?

A tender can allow for a particular gang, sequence and output. If those assumptions stay in the estimating file, the team delivering the work starts without the full picture.

Before a groundworks package starts, hand over:

• The scope, exclusions and outstanding clarifications
• Labour and plant allowances, with the outputs behind them
• The planned sequence, access and delivery assumptions
• Supplier quotes and what still needs ordering
• The main commercial risks and who will track them

Keep it practical. The site team needs to understand what the price allows for and flag when the job starts moving away from it.

Moore QS supports contractors with tendering and commercial management. Yorkshire-based, working nationwide.

Want a clearer handover from tender to site? Drop me a message.

The work has stopped. Has the hire charge?An excavator waiting for access. A pump kept “just in case”. A roller nobody h...
30/09/2026

The work has stopped. Has the hire charge?

An excavator waiting for access. A pump kept “just in case”. A roller nobody has arranged to off-hire.

Small gaps in plant control can quietly eat into a groundworks margin.

A useful weekly check:

• What plant is on hire against each job?
• Is it working, waiting or ready to leave?
• Who is responsible for arranging off-hire?
• Have off-hire confirmations been saved and invoices checked against them?

Check when charges stop under the agreed hire terms. Keep the off-hire reference and collection record together.

Moore QS provides practical commercial support for contractors. Yorkshire-based, working nationwide.

Want a clearer view of where your site costs are going? Drop me a message.

A variation isn’t secured because everyone on site knows about it.For every change, capture:• What changed from the pric...
28/09/2026

A variation isn’t secured because everyone on site knows about it.

For every change, capture:

• What changed from the priced scope
• Who instructed it and when
• Labour, plant and materials involved
• Any effect on programme or access
• How it has been valued and submitted

Site diaries and photos provide useful evidence, but they need to connect clearly to the commercial record.

Record the change early, price it promptly and track it through to agreement. Otherwise, completed work can remain as cost without becoming value.

Moore QS supports contractors with variations and practical commercial management. Yorkshire-based, working nationwide.

Need help getting your variations under control? Drop me a message.