The site has moved on. Has your programme?
Under NEC4 ECC, the Accepted Programme is a working commercial tool. Keeping it current helps the team understand progress, remaining work and the effects of change.
For groundworks and civils teams, a useful update should:
• Record actual progress and its effect on the remaining work.
• Show realistic sequencing, access requirements and interfaces with others.
• Explain how delays and notified Defects will be dealt with.
• Reflect time impacts even where compensation event status is unresolved—make that status clear.
Submit revisions for acceptance at intervals no longer than those stated in the Contract Data, and track the response. Keep a clear record of which revision is accepted.
A programme showing a delay does not, by itself, establish compensation event entitlement. Programme acceptance and the compensation event process need separate attention.
Check your NEC4 ECC requirements, Scope and amendments, including Z clauses.