24/04/2026
Project Update: Port of London Authority
We’re pleased to report solid progress on our project for the Port of London Authority, with a number of major milestones achieved.
• The Glulam and CLT frame forming the new fourth‑floor level and roof structure is now complete. Roof finishes and window installations are scheduled for the coming weeks.
• Structural alterations across all existing floors are finished, including the formation of a new lift shaft and stairwell.
• Internal fit‑out and first‑fix services are set to begin shortly.
With restricted site space, limited storage, and the sensitivity required near the Grade II listed pier and live client areas, the project has presented a logistical challenge, and it's been good to see the team rise to it.