1st Detached bungalow his ready for felt batten and tiling on Tuesday. 2nd detached bungalow has got a couple of hours w...
13/06/2026

1st Detached bungalow his ready for felt batten and tiling on Tuesday. 2nd detached bungalow has got a couple of hours work to the roof then that will be ready straight after the 1st one. More progress pictures to follow on these 2. The pair of semi detached bungalows have been dug out and foundations partially done due to the machines needing access to finish stoning up then foundations can be finished ready for the slab then we can get on with these, more progress pictures to follow on these
Liam Moran Ty Rochester Ridgeline Carpentry&Construction Mick Alty

Another one ready for the roof, 6 days building again from damp up to wall plate. Roof measure done. Pair of semi detach...
03/06/2026

Another one ready for the roof, 6 days building again from damp up to wall plate. Roof measure done. Pair of semi detached bungalows being dug out Monday so we’ll be getting cracking on them once passed and poured. Further progress pictures to follow

Detached bungalow number 2 ready for scaffold lift after just 3 days building. All loaded ready for backing up in block....
28/05/2026

Detached bungalow number 2 ready for scaffold lift after just 3 days building. All loaded ready for backing up in block. Aiming to have it all topped out ready for next Tuesday then another one is ready for a roof measure, further progress pictures to follow
Liam Moran Ty Rochester Alty grab hire ltd MKM

1st detached bungalow is all ready for the roof which will be around 10 days once the Trussies are ready. Onto the next ...
22/05/2026

1st detached bungalow is all ready for the roof which will be around 10 days once the Trussies are ready. Onto the next one which we’re hoping to have up ready for scaffolding next Friday. Further progress pictures to follow

Nice big meaty project we’ve got over in coppull. 2 detached bungalows and a pair of semi detached bungalows. We’ll be t...
19/05/2026

Nice big meaty project we’ve got over in coppull. 2 detached bungalows and a pair of semi detached bungalows. We’ll be taking these to water tight. 1st bungalow is ready for the 1st lift of scaffolding. This one should be ready for a roof measure on Friday, only taking us 6 days to build less the pikes. 2nd bungalow is ready for the concrete pour tomorrow allowing us to get the blue engineering round and internal blockwork up to damp then we can start building this one. Further progress pictures to follow
Liam Moran Ty Rochester Alty grab hire ltd MKM JRN Concrete Ltd

Double story extension over at Wigan is all ready for a reconfiguration to the roof which the customer is doing himself ...
16/05/2026

Double story extension over at Wigan is all ready for a reconfiguration to the roof which the customer is doing himself along with his own internals. We’ve took it as far as we can for him so it’s ready to hand over. We’ll be back on there in a couple of weeks to help him lift the new ridge beam on then piece the pikes in once the fascias are on and also put the sandstone heads and cills in, further progress pictures to follow Liam Moran Ty Rochester MKM Alty grab hire ltd

Further progress pictures of our latest double story extension over in Wigan. 4 days to get it to this point, all ready ...
01/05/2026

Further progress pictures of our latest double story extension over in Wigan. 4 days to get it to this point, all ready for the joist to go in. Further progress pictures to follow Liam Moran Ty Rochester Ryan Connor MKM

Nice little time filler over at Warrington. Bit of a garden freshen up. New flags, new charcoal border, new French doors...
27/04/2026

Nice little time filler over at Warrington. Bit of a garden freshen up. New flags, new charcoal border, new French doors in replace of old sliding doors and a new step. Liam Moran Ty RochesterMKM skips

New job started over in Wigan, double story extension. Suspended slab poured today ready for the brickwork to start, Fur...
27/04/2026

New job started over in Wigan, double story extension. Suspended slab poured today ready for the brickwork to start, Further progress pictures to follow. Now taking bookings for January 2027 👍
Liam Moran Ty Rochester Alty grab hire ltd JRN Concrete Ltd MKM

Our aspull job that we did last month, all the inside just been recently finished Liam Moran Ty Rochester
04/04/2026

Our aspull job that we did last month, all the inside just been recently finished Liam Moran Ty Rochester

Address

Wn2
Wigan
WN2

Alerts

Be the first to know and let us send you an email when Elite construction design and build ltd posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Elite construction design and build ltd:

Share