25/02/2026
N Aprtmnts / Site Update
-drywall installation completed
-thermal insulation system (base coat & mesh) completed
-external window and door frames installed
-air conditioning installation completed
-electrical and plumbing installation completed
-elevator installation completed
-surface preparation and first coat of paint completed
Next step: underfloor heating installation & floor screed and leveling works