07/06/2026
Excellent progress being made on Phase 2 & 3 at River Park, Cavan.
The first 24 houses of Phase 2 are now almost complete ready for tar, with only topsoiling, some final paving works, and a small amount of footpath and kerbing works remaining.
The final section of drainage for Phase 2 is currently being installed, and we expect to have all works completed within the next two weeks, leaving all phase 2 ready for surfacing.
In Phase 3, the last few house foundations are being piped and prepared for concrete pours as we continue to push the development forward.
Great credit to all the crews on site for the hard work and commitment shown throughout the project.
— P Kiernan Groundworks Ltd
.