Njenga structure,upto plaster(no tile ,paint,ceillings,wardrobes &kitchen cabinets)
0703 105 450
Foundation stones2500ft@60=ksh 150,000
Machine cut stones 3000@50=ksh 150,000
Ballast 3 Lorries @45,000=ksh135,000
River sand 4 Lorries @45,000=ksh 180,000
Cements ,bags700@800=ksh 560,000
Hardcore ,6 rorries@30,000=ksh 180,000
Quarry dust blinding,3 lorries@30,000=ksh,90,000
Reinforcements
D10, 80@900=ksh 72,000
D8,70 @600=KSH 42,000
D12 ,60@1300=Ksh,78,000
BRC,3 Roll@34000=ksh,102,000
Binding wire, 3 rolls@4000=ksh12,000
Dump proof membranes,4 rolls@4000=ksh16,000
Dpc,4 roll@4000=ksh 16,000
Timbers
6x1 ,2500 ft@25=ksh 62,500
Roof timbers7000ft@25=ksh175,000
Roofing sheets,box profile=ksh,250,000
Ordinary nails,4 inch,100kg@200=ksh 20,000
Roofing nails,100kg@200=ksh 20,000
Steel windows & doors=ksh, 150,000
Timber doors=ksh 80,000
Plumbing electrical materials ,=ksh 200,000
Sub- Total=2,740,500
Labour,30% 822,150
Total =3,562,650
Njenga structure,upto plaster(no tile ,paint,ceillings,wardrobes &kitchen cabinets)
0703 105 450
Foundation stones2500ft@60=ksh 150,000
Machine cut stones 3000@50=ksh 150,000
Ballast 3 Lorries @45,000=ksh135,000
River sand 4 Lorries @45,000=ksh 180,000
Cements ,bags700@800=ksh 560,000
Hardcore ,6 rorries@30,000=ksh 180,000
Quarry dust blinding,3 lorries@30,000=ksh,90,000
Reinforcements
D10, 80@900=ksh 72,000
D8,70 @600=KSH 42,000
D12 ,60@1300=Ksh,78,000
BRC,3 Roll@34000=ksh,102,000
Binding wire, 3 rolls@4000=ksh12,000
Dump proof membranes,4 rolls@4000=ksh16,000
Dpc,4 roll@4000=ksh 16,000
Timbers
6x1 ,2500 ft@25=ksh 62,500
Roof timbers7000ft@25=ksh175,000
Roofing sheets,box profile=ksh,250,000
Ordinary nails,4 inch,100kg@200=ksh 20,000
Roofing nails,100kg@200=ksh 20,000
Steel windows & doors=ksh, 150,000
Timber doors=ksh 80,000
Plumbing electrical materials ,=ksh 200,000
Sub- Total=2,740,500
Labour,30% 822,150
Total =3,562,650