03/08/2024
03.08.2024
New Ascott Hotel (144 Rooms) with Banquet Hall , Project at the famous Upper Penang Road.
Site Walkabout Inspection & Discussion with Boss, Respective Consultants and Project Team.
The current progress is currently at 80% completion status.
Boss has push deadline to get all our finishing, ID & Fit-in Works physically completed by next quarter.
As such, we will need to increase our resources & fast track respective scope of work now.