19/08/2026
• More than 560 people are working on site across four Namibian contractors.
• The project has achieved approximately 1.1 million work hours without a lost-time injury.
• Bulk earthworks are 92% complete, while over 10,800 m³ of concrete has been placed.
• Phase 1 of the permanent water supply pipeline is approximately 87% complete.
• Local contractors and Namibian-owned SMEs continue to benefit from construction opportunities at Etango.
Etango early works reach 92% completion
Construction early works at Bannermans Etango Uranium Project are moving rapidly, with the critical 24-month bulk earthworks contract now approximately 92% complete.
Bannerman Energy Managing Director and Chief Executive Gavin Chamberlain, confirmed today that activities are tracking squarely on budget and schedule.
Chamberlain said that Earthworks are currently concentrated on defining the heap leach pad, wet plant terraces, and process solution ponds, making the overall physical footprint of the future mine increasingly visible on site.
“Of particular note is that the 24- month bulk earthworks contract is now more than 90% complete, a substantial achievement and a key investment in derisking the critical path for full-scale construction of the Etango Project,” he said.