How to calculate the quantity of concrete in Pier & Pier & Pier Cap.​ ​ ​ ​ ​ ​
03/01/2026

How to calculate the quantity of concrete in Pier & Pier & Pier Cap.






ESTIMATES💲USED IN CONSTRUCTION AND CIVIL ENGINEERING WORKS.🏗🦺Construction and civil engineering use various estimates fr...
08/12/2025

ESTIMATES💲USED IN CONSTRUCTION AND CIVIL ENGINEERING WORKS.🏗🦺

Construction and civil engineering use various estimates from rough conceptual stages (Preliminary, Plinth Area, Cube Rate) to highly detailed ones (Detailed Estimate, Item Rate), serving different purposes like feasibility, bidding, and cost control, including specific types for repairs (Annual Repair) or project changes (Revised, Supplementary).

These estimates progress from general overviews with wide variance to precise calculations using measured quantities and rates.

APPROXIMATE/PRELIMINARY ESTIMATES

1. Preliminary/Rough Order of Magnitude (ROM) Very early, high-level cost for feasibility, using limited info (e.g., cost per square meter/feet).

2. Plinth Area Estimate
Based on building's plinth area and historical rates per plinth area.

3. Cube Rate Estimate (Cubical Content)
Plinth area multiplied by height; useful for multi-story buildings.

4. Approximate Quantity Method
Estimates based on total length of walls or similar linear measurements.

DETAILED ESTIMATES

1. Detailed Estimate/Item Rate Estimate
Most accurate, measuring quantities of each item (e.g., concrete, bricks) from drawings and applying unit rates.

2. Quantity Estimate
Focuses on precise material quantities needed (e.g., tiles, sand).

3. Bid Estimate/Contractor's Estimate
Prepared by contractors for bidding, including overheads, profit, and risk.

4. Engineer's Estimate
Owner's/consultant's detailed estimate for comparison.

CONTROL & PROJECT MANAGEMENT ESTIMATES

[During Ex*****on]

1. Cost Control Estimate
A working estimate to track costs against the budget throughout the project.

2. Revised Estimate
Prepared when original sanctioned estimates need significant changes (scope, unforeseen conditions).

3. Supplementary Estimate
For new, unforeseen items of work not in the original estimate.

4. Final Estimate
The final calculated cost after project completion.

SPECIALIZED ESTIMATES

1. Annual Repair/Maintenance Estimate
For routine upkeep and repairs of completed works.

2. Parametric Estimate
Uses statistical relationships (e.g., cost per km of road) for large infrastructure.

3. Analogous Estimate
Uses costs from similar past projects for early-stage comparison.






RCC footing details in construction
08/12/2025

RCC footing details in construction

The Bodo-Bonny Road finally had a temporary opening today, commissioned by The Hon. Minister for Works, Sen. Dave Nweze ...
08/12/2025

The Bodo-Bonny Road finally had a temporary opening today, commissioned by The Hon. Minister for Works, Sen. Dave Nweze Umahi, with the Secretary of State, and other important Bonny local government representatives present.

It’s so exciting to see progress being made on this important route. This temporary opening means a lot for local communities and businesses. I can only imagine the relief and joy this brings to everyone especially in this festive period.

However, the opening comes with some conditions, such as a tolling system and a temporary ban on heavy equipment and trucks.

The road would be open between 7 a.m. and 5 p.m. There might be another closure for the final completion sometime next year, but that isn't clear yet.

I'm trusting there will be security checks throughout the length and breadth of the road.

For now, let's drive with caution and stay vigilant.

Special thanks to , the Federal Government of Nigeria, and Nigeria for this great feat.

📸 Ph Drones x Bonny LGA media


“Concrete stairs in progress… every shape, every style 😅Straight, curved, rough — but all heading to the same place: up!...
07/12/2025

“Concrete stairs in progress… every shape, every style 😅
Straight, curved, rough — but all heading to the same place: up!
Construction life never looks clean at first, but trust the process 👷‍♂️🧱💪”

Address

Ahoada
Port Harcourt
510101

Opening Hours

Monday 09:00 - 17:00
Tuesday 09:00 - 17:00
Wednesday 09:00 - 17:00
Thursday 09:00 - 17:00
Friday 09:00 - 17:00
Saturday 09:00 - 17:00

Website

Alerts

Be the first to know and let us send you an email when Pee Tech posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share